Where things stand: Proposed Announced in July 2026 as part of a $1.5 billion plan to reuse the closed paper mill site.
❓ 3 open questions about it: see below.
Last checked Oct 12, 2026.
🕒 Latest update (Oct 2026): The local chamber of commerce asked the city to write early rules for data centers, such as independent reviews of water, noise and power. The council and planning commission are considering them.
What we know
- 📍 WhereFormer Pixelle paper mill site, Chillicothe, Ross County
- 🏢 CompanyU.S. Paper Mill Company LLC (site owner) with Aligned
- 👤 Built forAligned (computing campus using AMD hardware)
- 🌳 Size6.5 acres
- ⚡ Power it needs85 megawatts (about as much as 68,000 homes)
- 💸 Tax breaksThe company says it has not asked for any tax break.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How big will the Aligned data center at the paper mill be, in megawatts and buildings? 🙋 I'll find out ·
- Would it use the mill's old water and power hookups? 🙋 I'll find out ·
- News reports name the data center company differently (Aligned, 'Aligned Engine', 'Alignment Engine'). Which company is it exactly? 🙋 I'll find out ·
What happened so far
- July 2026The new owner of the closed paper mill named Aligned as a data center tenant in a $1.5 billion reuse plan.
- Sept 8, 2026At a public meeting at Chillicothe High School, the data center company said it would not ask for tax breaks. Some council members said they were asked to sign a privacy agreement (NDA) to tour the site.
- Sept 14, 2026Chillicothe repealed the data center pause it had passed in August.
- Oct 2026The local chamber of commerce asked the city to write early rules for data centers, such as independent reviews of water, noise and power. The council and planning commission are considering them.
Drag the slider to compare the land before and now.
Where this comes from
- Data center and more new tenants expected for shuttered Chillicothe paper mill site · WYSU · July 6, 2026
- OpenStreetMap Nominatim result for Pixelle Chillicothe · OpenStreetMap contributors · Oct 7, 2026
- Chillicothe demands transparency as data center details emerge amid NDA scandal · WSYX ABC6 · Sept 8, 2026
- How Chillicothe's paper mill could become a data center · NBC4 WCMH-TV · Sept 2026
- Chillicothe demands transparency as data center details emerge amid NDA scandal · ABC6 / WSYX · Sept 8, 2026
- Chillicothe Chamber of Commerce calls for data center framework · NBC4 WCMH-TV · Oct 2026