Amazon data center campus south of Trenton (Madison and St. Clair townships)
Amazon wants to build 18 data center buildings on 601 acres of farmland south of Trenton. The land would need to be annexed into the city. Both townships said no, and the county commissioners will make the final call.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Township Trustees of Madison Township.
Where things stand: Proposed Trenton withdrew its petition to annex the land in September 2026, so no county hearing was held. The petitioners kept the right to file again.
❓ 4 open questions about it: see below.
Last checked Nov 16, 2026.
🕒 Latest update (Nov 10, 2026): The Butler County Planning Commission and the St. Clair Township Zoning Commission approved a zoning change that would block data centers as a main land use in the township. Township trustees have the final say.
What we know
- 📍 WhereBetween Wayne Madison Road and Hawkins Road, toward Augspurger Road and the Great Miami River; land is in both Madison and St. Clair townships, Madison, Butler County
- 🏢 CompanyAmazon Web Services
- 👤 Built forAmazon
- 🌳 Size601 acres
- 🔌 Where the power comes fromNext to Duke Energy power lines and Duke's Madison gas power plant.
- 💵 Cost$5 billion
- 💸 Tax breaksAmazon offered each township $5 million plus property taxes.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Will the planned Trenton voter ban on data centers apply here if the land is annexed? 🙋 I'll find out ·
- How much power and water would the campus use? 🙋 I'll find out ·
- Will Amazon or the landowners file a new annexation petition, or ask Madison or St. Clair Township directly? 🙋 I'll find out ·
- Will St. Clair Township trustees approve the zoning change that blocks data centers? 🙋 I'll find out ·
What happened so far
- Aug 12, 2026News reports said Amazon is negotiating an 18-building, $5 billion campus on 601 acres south of Trenton.
- Aug 27, 2026St. Clair and Madison township leaders rejected the petition to annex the land into Trenton.
- Sept 15, 2026Butler County commissioners accepted the withdrawal of the petition to annex the 601 acres into Trenton, and the annexation hearing was canceled. The petitioners said they may file again.
- Nov 10, 2026The Butler County Planning Commission and the St. Clair Township Zoning Commission approved a zoning change that would block data centers as a main land use in the township. Township trustees have the final say.
Local votes and rules
🗺️ Zoning change
The township zoning commission and the county planning commission approved a zoning change that would block data centers as a main land use in the township. The township trustees must approve it before it takes effect.
⏸️ Pause on new data centers
Butler County commissioners passed a six-month pause (moratorium) on new data centers in six townships where the county controls zoning, including Madison Township. It is set to end in December 2026.
Drag the slider to compare the land before and now.
Where this comes from
- Amazon eyes Greater Cincinnati suburb for $5B data center · WKRC Local 12 · Aug 12, 2026
- Leaders turn down millions, reject annexation plan for Amazon data center · Spectrum News 1 · Aug 27, 2026
- Public hearing canceled after Trenton withdraws annexation petition for proposed Amazon data center · WCPO · Sept 15, 2026
- $5 Billion 601-acre Amazon data center: Annexation Petition Withdrawn Ahead of Trenton Vote · Construction Review Online · Sept 17, 2026
- Saint Clair Township moves to block data centers after neighboring Trenton voters reject large-scale projects · WCPO · Nov 11, 2026
See something wrong? Tell us and we'll fix it.