ProposedBig (AI-size): 601 acres

Amazon data center campus south of Trenton (Madison and St. Clair townships)

Amazon wants to build 18 data center buildings on 601 acres of farmland south of Trenton. The land would need to be annexed into the city. Both townships said no, and the county commissioners will make the final call.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Trustees of Madison Township.

Where things stand: Proposed Trenton withdrew its petition to annex the land in September 2026, so no county hearing was held. The petitioners kept the right to file again.

❓ 4 open questions about it: see below.

Last checked Nov 16, 2026.

🕒 Latest update (Nov 10, 2026): The Butler County Planning Commission and the St. Clair Township Zoning Commission approved a zoning change that would block data centers as a main land use in the township. Township trustees have the final say.

What we know

  • 📍 WhereBetween Wayne Madison Road and Hawkins Road, toward Augspurger Road and the Great Miami River; land is in both Madison and St. Clair townships, Madison, Butler County
  • 🏢 CompanyAmazon Web Services
  • 👤 Built forAmazon
  • 🌳 Size601 acres
  • 🔌 Where the power comes fromNext to Duke Energy power lines and Duke's Madison gas power plant.
  • 💵 Cost$5 billion
  • 💸 Tax breaksAmazon offered each township $5 million plus property taxes.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will the planned Trenton voter ban on data centers apply here if the land is annexed? 🙋 I'll find out ·
  • How much power and water would the campus use? 🙋 I'll find out ·
  • Will Amazon or the landowners file a new annexation petition, or ask Madison or St. Clair Township directly? 🙋 I'll find out ·
  • Will St. Clair Township trustees approve the zoning change that blocks data centers? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Aug 12, 2026
      News reports said Amazon is negotiating an 18-building, $5 billion campus on 601 acres south of Trenton.
    • Aug 27, 2026
      St. Clair and Madison township leaders rejected the petition to annex the land into Trenton.
    • Sept 15, 2026
      Butler County commissioners accepted the withdrawal of the petition to annex the 601 acres into Trenton, and the annexation hearing was canceled. The petitioners said they may file again.
    • Nov 10, 2026
      The Butler County Planning Commission and the St. Clair Township Zoning Commission approved a zoning change that would block data centers as a main land use in the township. Township trustees have the final say.

    Local votes and rules

    🗺️ Zoning change

    The township zoning commission and the county planning commission approved a zoning change that would block data centers as a main land use in the township. The township trustees must approve it before it takes effect.

    Nov 10, 2026

    ⏸️ Pause on new data centers

    Butler County commissioners passed a six-month pause (moratorium) on new data centers in six townships where the county controls zoning, including Madison Township. It is set to end in December 2026.

    June 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something