Send us a tip
Approved, not built yet

Google data center near Lima (Project BOSC)

Also called: Project BOSC

Google plans a $500 million data center in American Township, north of Lima. It will pay for new roundabouts and water upgrades, and give Elida schools $250,000 a year in place of some taxes.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Trustees of American Township.

Where things stand: Approved, not built yet Google was named in March 2026. A 20-year water deal with Lima was announced in May 2026. Construction expected to start in 2026.

❓ 4 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (May 6, 2026): Allen County development group announced a 20-year water deal with Lima and $13.7 million in water upgrades.

What we know

  • 📍 WhereNorth of Lima, near North Cole Street, Bluelick Road and State Route 115, American, Allen County
  • 🏢 CompanyGoogle
  • 👤 Built forGoogle
  • 💧 WaterCity of Lima (20-year agreement, $13.7 million in water upgrades)
  • 💵 Cost$500 million
  • 💸 Tax breaks15-year tax break. Google pays Elida Local Schools $250,000 a year to make up for it.
  • 👷 Jobs promised50

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which township is Project BOSC in? 2026 reports say American Township, but a 2025 Allen County development group post said Shawnee and Perry townships. 🙋 I'll find out ·
  • How much water will it use each day? 🙋 I'll find out ·
  • Has Ohio EPA approved an air permit for its backup diesel generators? 🙋 I'll find out ·
  • How many acres and megawatts? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • March 18, 2026
      Google was revealed as the company behind the $500 million Project BOSC.
    • May 6, 2026
      Allen County development group announced a 20-year water deal with Lima and $13.7 million in water upgrades.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Google data center under development near Lima · Crescent-News · March 18, 2026
    2. Project BOSC · Allen Economic Development Group · May 6, 2026
    3. 2025 brings strong investments to Allen County · Allen Economic Development Group · 2025