Greenidge runs a gas power plant and bitcoin mine on Seneca Lake. The company says it wants to turn the site into an AI data center and has asked the grid operator for 200 MW more power. No town application has been reported.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Town Board of Torrey Town.

Where things stand: Proposed The company, now called Vulcan Infrastructure and Power, plans to shift the bitcoin mine at the gas plant to AI computing. It has a proposed 60 MW grid deal and has asked for more grid power. The town says no application has been filed.

❓ 3 open questions about it: see below.

Last checked Oct 15, 2026.

🕒 Latest update (July 24, 2026): Greenidge Generation Holdings renamed itself Vulcan Infrastructure and Power (stock ticker changed from GREE to VIP) and said its main business will shift from crypto mining to AI computing.

What we know

  • 📍 WhereGreenidge power plant, 590 Plant Road, Dresden, on Seneca Lake, Torrey, Yates County
  • 🏢 CompanyGreenidge Generation Holdings
  • ⚡ Power it needs200 megawatts (about as much as 160,000 homes)
  • 🔌 Where the power comes fromIts own gas power plant on site, plus up to 60 MW from NYSEG's grid (proposed deal) and a 200 MW grid request under study.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Has Greenidge filed any plans with the Town of Torrey for an AI data center? 🙋 I'll find out ·
  • Will the plant take more Seneca Lake water for cooling? 🙋 I'll find out ·
  • How much grid power has Vulcan asked for at Dresden? Reports name 200 MW and 260 MW. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the map. OpenStreetMap shows the Greenidge power plant and data center on Seneca Lake at Dresden. We put the pin on the plant.

    What happened so far

    • March 5, 2026
      Greenidge said it got approval for 60 MW of steady grid power at Dresden and started a NYISO study for 200 MW more, for AI/computing data centers. It also settled its long fight with DEC over the plant's air permit.
    • May 18, 2026
      Greenidge said NYSEG sent a proposed grid deal for 60 MW at Dresden.
    • July 24, 2026
      Greenidge Generation Holdings renamed itself Vulcan Infrastructure and Power (stock ticker changed from GREE to VIP) and said its main business will shift from crypto mining to AI computing.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Greenidge Generation reports 2025 preliminary results, obtains 100 MW power approval for datacenter expansion · The Energy Mag · March 5, 2026
    2. Greenidge Generation reports first quarter 2026 results and advances AI/HPC infrastructure expansion · Greenidge Generation (press release) · May 18, 2026
    3. Greenidge Power Plant and Data Center · OpenStreetMap · Oct 8, 2026
    4. Greenidge shifts to data center, new name · Finger Lakes Times · Aug 1, 2026
    5. Torrey residents plan Oct. 13 forum on Vulcan data center proposal · FingerLakes1.com · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.