πŸ“£ Report Something
USA β€Ί New York β€Ί Erie County β€Ί Tonawanda Town
Stopped or cancelled

Riverview Innovation & Technology Campus data center (former Tonawanda Coke site)

Also called: RITC data center

Developers who are cleaning up the old Tonawanda Coke plant want to build a $2 billion, 300 MW AI data center there. It would use about as much power as Tonawanda and Amherst combined. Review is paused, and the town passed a one-year moratorium.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Paused: the developer asked to pause review in June 2026 while it waits on grid studies, and the town passed a one-year moratorium on data centers of 20 MW or more in Aug. 2026.

πŸ•’ Latest update (Aug 3, 2026): Town of Tonawanda Town Board unanimously passed a one-year moratorium on data centers of 20 MW or more.

What we know

  • πŸ“ Where3875 River Road (former Tonawanda Coke plant), Tonawanda, Erie County
  • 🏒 CompanyRiverview Innovation & Technology Campus (Ontario Specialty Contracting owners)
  • 🌳 Size140 acres
  • ⚑ Power it needs300 megawatts (about as much as 240,000 homes)
  • πŸ”Œ Where the power comes fromState grid (National Grid) through a planned $50 million substation; developer says most power would come from the Niagara hydro plant and Nine Mile Point nuclear plant.
  • πŸ’΅ Cost$2 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • 2025
    Developer proposed a 500,000 sq ft, 300 MW AI data center on the old coke plant land.
  • June 2026
    Site plan talk was pulled from the town planning board agenda; the developer paused review while waiting on NYISO and National Grid.
  • Aug 3, 2026
    Town of Tonawanda Town Board unanimously passed a one-year moratorium on data centers of 20 MW or more.

Local votes and rules

⏸️ Pause on new data centers

Town board unanimously paused new applications for data centers of 20 megawatts or more for one year. It covers the planned data center at the old Tonawanda Coke site.

Aug 3, 2026
πŸ›°οΈ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Proposed $2B AI data center at former industrial site raises questions in Town of Tonawanda Β· WKBW Β· 2025
  2. Data center project at former Tonawanda Coke site on hold Β· Buffalo Toronto Public Media Β· June 3, 2026
  3. Tonawanda Town Board passes data center moratorium Β· Buffalo Toronto Public Media Β· Aug 4, 2026

See something wrong? Tell us and we'll fix it.