Stopped or cancelledBig (AI-size): 300 megawatts

Riverview Innovation & Technology Campus data center (former Tonawanda Coke site)

Also called: RITC data center

Developers who are cleaning up the old Tonawanda Coke plant want to build a $2 billion, 300 MW AI data center there. It would use about as much power as Tonawanda and Amherst combined. Review is paused, and the town passed a one-year moratorium.

✔ ConfirmedSourceLast checked: Oct 7, 2026

What happens next?

Where things stand: Stopped or cancelled Paused: the developer asked to pause review in June 2026 while it waits on grid studies, and the town passed a one-year moratorium on data centers of 20 MW or more in Aug. 2026.

❓ 2 open questions about it: see below.

📣 See work going on anyway? Tell us

Last checked Oct 7, 2026.

🕒 Latest update (Aug 3, 2026): Town of Tonawanda Town Board unanimously passed a one-year moratorium on data centers of 20 MW or more.

What we know

  • 📍 Where3875 River Road (former Tonawanda Coke plant), Tonawanda, Erie County
  • 🏢 CompanyRiverview Innovation & Technology Campus (Ontario Specialty Contracting owners)
  • 🌳 Size140 acres
  • ⚡ Power it needs300 megawatts (about as much as 240,000 homes)
  • 🔌 Where the power comes fromState grid (National Grid) through a planned $50 million substation; developer says most power would come from the Niagara hydro plant and Nine Mile Point nuclear plant.
  • 💵 Cost$2 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water would the data center use per day? 🙋 I'll find out ·
  • Is the site 120 or 140 acres? Reports differ. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • 2025
      Developer proposed a 500,000 sq ft, 300 MW AI data center on the old coke plant land.
    • June 2026
      Site plan talk was pulled from the town planning board agenda; the developer paused review while waiting on NYISO and National Grid.
    • Aug 3, 2026
      Town of Tonawanda Town Board unanimously passed a one-year moratorium on data centers of 20 MW or more.

    Local votes and rules

    ⏸️ Pause on new data centers

    Town board unanimously paused new applications for data centers of 20 megawatts or more for one year. It covers the planned data center at the old Tonawanda Coke site.

    Aug 3, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Proposed $2B AI data center at former industrial site raises questions in Town of Tonawanda · WKBW · 2025
    2. Data center project at former Tonawanda Coke site on hold · Buffalo Toronto Public Media · June 3, 2026
    3. Tonawanda Town Board passes data center moratorium · Buffalo Toronto Public Media · Aug 4, 2026