Send us a tip
Proposed

Sugar Hill golf course data center idea (Portland)

Also called: The Four Winds of Lake Erie

Weed Inc. wants to turn the closed 44-acre Sugar Hill golf course on Route 5 into a data center campus. The Portland Town Board passed a resolution supporting the idea in general, but no plans have been filed. Many residents oppose it, and a petition against it got more than 3,500 signatures.

👥 Reported, not confirmed yetSourceLast checked: Oct 7, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Town Board of Portland Town.

Where things stand: Proposed Town board backed the idea in March 2026, but no application has been filed. Data centers are not allowed under Portland's zoning now.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (July 2026): Residents asked the board to cancel its resolution; no board member made a motion to do so.

What we know

  • 📍 WhereFormer Sugar Hill Golf Course, 7060 East Lake Road (Route 5), near Lake Erie, Portland, Chautauqua County
  • 🏢 CompanyThe Four Winds of Lake Erie, LLC
  • 🏛️ Owned byWeed Inc.
  • 🌳 Size44 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Has Weed Inc. filed any plans with the Town of Portland? 🙋 I'll find out ·
  • How many megawatts would the data center use? 🙋 I'll find out ·
  • Where would its water come from? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • March 11, 2026
      Portland Town Board passed a resolution giving general support to a data center idea at Sugar Hill.
    • July 2026
      Residents asked the board to cancel its resolution; no board member made a motion to do so.

    Local votes and rules

    📌 Other

    Town board passed a resolution giving general support to the idea of a data center at the old Sugar Hill golf course, while keeping full review for later. In July 2026 residents asked the board to cancel it; no member moved to do so. Data centers are still not allowed under the town code.

    March 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something