Eco-Yotta data center plan on County Highway 9 (Town of Oneonta)

EcoYotta bought more than 150 acres on County Highway 9 in 2024 and proposed a data center of about 2 million square feet. It asked to rezone the farm and home land. The plan was later described as an AI research or hydroponics hub. After strong opposition, the town passed a 12-month moratorium in May 2026.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Paused. The Town of Oneonta passed a 12-month moratorium on AI data centers and crypto mines in May 2026.

πŸ•’ Latest update (May 2026): Town Board voted unanimously for a 12-month moratorium on AI data centers and crypto mines.

What we know

  • πŸ“ Where357 County Highway 9, Oneonta, Otsego County
  • 🏒 CompanyEcoYotta Inc.
  • 🌳 Size150 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Oct 2024
    EcoYotta bought the land on County Highway 9.
  • June 11, 2025
    EcoYotta presented its plan; the planning board received the application.
  • Dec 9, 2025
    EcoYotta presented a business plan to the Town Board.
  • May 2026
    Town Board voted unanimously for a 12-month moratorium on AI data centers and crypto mines.

Local votes and rules

⏸️ Pause on new data centers

Town board unanimously passed a 12-month pause on AI data centers and crypto mines, after more than 700 residents signed a petition about the Eco-Yotta plan. The supervisor said the board wants a permanent ban next.

May 2026
πŸ›°οΈ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Community members raise concerns about proposed data center Β· The Daily Star Β· Aug 13, 2025
  2. Eco-Yotta presents business plan to Oneonta board, criticizes process Β· Vertical Farm Daily Β· Dec 19, 2025
  3. Oneonta town board approves 12-month moratorium on AI data centers, crypto mining facilities Β· WBNG Β· May 15, 2026

See something wrong? Tell us and we'll fix it.