A company called Ranalli Super DC asked to connect a 300 MW data center to the grid on land off Hencle Boulevard in Lysander. No town application has been filed. The town paused all data center applications for 6 months while it writes rules.

πŸ‘₯ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: Only a grid (NYISO) request so far; no town or DEC application. The town passed a 6-month moratorium in May 2026.

πŸ•’ Latest update (June 15, 2026): Onondaga County started a $500,000 study to guide towns on data centers, after Lysander asked for help.

What we know

  • πŸ“ WhereAbout 124 acres off Hencle Boulevard and Oswego Road (22 Hencle Blvd.), near Baldwinsville, Lysander, Onondaga County
  • 🏒 CompanyRanalli Super DC LLC
  • 🌳 Size124 acres
  • ⚑ Power it needs300 megawatts (about as much as 240,000 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • 2026
    Town Supervisor said no DEC permit or application has been filed for a data center on the parcel.
  • May 2026
    Lysander Town Board unanimously passed a 6-month moratorium on data centers.
  • June 15, 2026
    Onondaga County started a $500,000 study to guide towns on data centers, after Lysander asked for help.

Local votes and rules

⏸️ Pause on new data centers

Town board unanimously passed a 6-month pause on data centers, after more than 350 residents came out against a possible data center on land off Hencle Boulevard and Oswego Road.

May 7, 2026
πŸ›°οΈ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Onondaga County launches $500K study to guide towns on AI data centers Β· CNY Central Β· June 15, 2026
  2. State moratorium does not halt local review of proposed Lysander data center Β· CNY Central Β· 2026

See something wrong? Tell us and we'll fix it.