Send us a tip
ProposedBig (AI-size): 400 megawatts

TeraWulf data center at the old Cayuga power plant (Lansing)

Also called: Lake Hawkeye, Cayuga Data Campus, Cayuga Compute, Cayuga Data

TeraWulf leased the old Cayuga coal plant on Cayuga Lake for 80 years and wants to build an AI data center there, up to 400 megawatts. The town zoning board let it go ahead as 'general processing' in a 3-2 vote. Many residents oppose it, and more than 20,000 people signed a petition against it.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Town Board of Lansing Town.

Where things stand: Proposed Town zoning appeal approved in Dec. 2025; the planning board said the site plan was incomplete in April 2026. A lawsuit is ongoing.

❓ 4 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (July 14, 2026): The governor paused state environmental permits for data centers of 50 megawatts or more. TeraWulf said its local planning process goes on.

What we know

  • 📍 WhereFormer Cayuga (Milliken) coal plant, 228 Cayuga Drive, on the east shore of Cayuga Lake, Lansing, Tompkins County
  • 🏢 CompanyTeraWulf
  • 👤 Built forLeased to AI companies; the Cornell Sun says clients include Alphabet
  • 🌳 Size183 acres
  • ⚡ Power it needs400 megawatts (about as much as 320,000 homes)
  • 🔌 Where the power comes fromState power grid, through the old power plant's grid connection.
  • 💧 WaterBolton Point public water system (company says lake water only for dust control and washing)
  • ❄️ CoolingClosed-loop dry cooling with fans (company claim)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Has TeraWulf completed its site plan application with the Lansing Planning Board? 🙋 I'll find out ·
  • Does the state permit pause (Executive Order 62) apply to any state permit this project still needs? 🙋 I'll find out ·
  • How many diesel backup generators are planned? 🙋 I'll find out ·
  • What has the court decided in the lawsuit against the project? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the county tax roll. The old Cayuga power plant is the 54-acre lot at 228 Cayuga Drive owned by Cayuga Operating Co. LLC; the same company owns 379 acres next to it on Ridge Road. We put the pin on the plant lot.

    What happened so far

    • Aug 14, 2025
      TeraWulf announced an 80-year lease on the old Cayuga power plant site for an AI data center.
    • Nov 19, 2025
      Lansing Town Board withdrew a proposed one-year building moratorium.
    • Dec 22, 2025
      Town voted 3-2 to accept TeraWulf's appeal to call the data center 'general processing', so no rezoning is needed.
    • Jan 2026
      Environmental groups filed a lawsuit against the project.
    • April 2026
      State DEC approved taking up to about 1 million gallons a day from Cayuga Lake for the site.
    • April 27, 2026
      Lansing Planning Board said TeraWulf's application was incomplete.
    • April 29, 2026
      A court ruled the groups suing have standing, so the case goes on.
    • June 17, 2026
      Opponents delivered a petition with about 20,900 signatures to the town.
    • July 14, 2026
      The governor paused state environmental permits for data centers of 50 megawatts or more. TeraWulf said its local planning process goes on.

    Local votes and rules

    🚫 Ban

    At a special meeting on Sept. 29, 2026, the Lansing Town Board asked the town attorney to write a local law banning data centers. Nothing is in effect yet. The board must still introduce it and hold a public hearing. TeraWulf's plan is still under Planning Board review.

    Sept 29, 2026

    ⚖️ Court case

    Two environmental groups (FLX Strong and Cayuga Environmental Action Now) sued TeraWulf and the Lansing Zoning Board of Appeals over the 'general processing' ruling. In late April 2026 a judge refused to throw out the case, so it goes on.

    Jan 2026

    ✅ Approved

    In a 3-2 vote, the town accepted TeraWulf's appeal to call its data center at the old Cayuga power plant 'general processing'. That means no rezoning or variance is needed.

    Dec 22, 2025

    📌 Other

    Town board unanimously withdrew a proposed one-year building pause. That let the TeraWulf AI data center plan at the old Cayuga power plant move ahead.

    Nov 19, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something