Stopped or cancelledBig (AI-size): Described as an AI or hyperscale project in the sources

Wildflower AI data center in Yaphank

Also called: Brookhaven Logistics Center

Developer Wildflower wants to turn empty warehouses in Yaphank into an AI data center worth over $1 billion. Residents and town leaders raised worries about power, water and noise. In July 2026 Brookhaven passed an 18-month data center moratorium.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

Where things stand: Stopped or cancelled On hold: Brookhaven passed an 18-month data center moratorium in July 2026, and the state paused permits for big data centers.

❓ 2 open questions about it: see below.

📣 See work going on anyway? Tell us

Last checked Oct 8, 2026.

🕒 Latest update (July 16, 2026): Brookhaven Town Board approved an 18-month data center moratorium after a long hearing.

What we know

  • 📍 Where1001 Expressway Drive North, Yaphank (71-acre warehouse lot along the Long Island Expressway), Brookhaven, Suffolk County
  • 🏢 CompanyWildflower
  • ❄️ CoolingClosed-loop cooling; one-time fill of about 700,000 gallons
  • 💵 Cost$1 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many megawatts would the Yaphank data center use? 🙋 I'll find out ·
  • Has Wildflower applied to the Suffolk County Water Authority? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the county tax roll. The warehouse lot at 1001 Expressway Drive North in Yaphank (71 acres) is held through the Brookhaven IDA for WF Industrial XII LLC, a Wildflower company. We put the pin there.

    What happened so far

    • June 25, 2026
      Town supervisor proposed an 18-month data center moratorium after the Yaphank plan became public.
    • July 14, 2026
      Governor paused state environmental permits for data centers of 50 megawatts or more.
    • July 16, 2026
      Brookhaven Town Board approved an 18-month data center moratorium after a long hearing.

    Local votes and rules

    ⏸️ Pause on new data centers

    After a nearly six-hour hearing, the town board passed an 18-month pause on new data centers. Town planners must write zoning rules, because the town code does not define data centers yet.

    July 16, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Proposed AI data center in Yaphank meets opposition from residents and town leaders · News 12 Long Island · June 25, 2026
    2. Brookhaven approves 18-month data center moratorium after marathon hearing · Fire Island News · July 24, 2026
    3. Key Takeaways from New York Data Center Permitting Pause Under Executive Order No. 62 · Davis Wright Tremaine · July 2026