Send us a tip
ProposedBig (AI-size): 180 megawatts

Kenwood Commons data center (Albany South End)

Also called: Kenwood Tech Center

Guild Ventures wants to build a 250,000-square-foot data center on the empty 76-acre Kenwood site in Albany, along with about 300 homes. It says the data center would have 125 to 175 jobs. It asked the state grid operator for 180 megawatts for the whole site. No zoning request has been filed yet, and many residents oppose it.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Albany City.

Where things stand: Proposed No formal application yet. Developers asked the grid operator for 180 megawatts and hope to open in Dec. 2028.

❓ 4 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Aug 2026): Developers held a community meeting; about 75 people came. They said they will apply for zoning changes in weeks or months.

What we know

  • 📍 Where451 Southern Blvd. (former Kenwood convent / Doane Stuart School land, about 74 acres), Albany, Albany County
  • 🏢 CompanyGuild Ventures
  • 🏛️ Owned byEKG
  • 🌳 Size76 acres
  • ⚡ Power it needs180 megawatts (about as much as 144,000 homes)
  • ❄️ CoolingAir cooling (developer says little water use)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How big is the data center? WAMC (Aug. 2026) reported 250,000 square feet; The Real Deal (June 2026) reported 500,000 square feet. 🙋 I'll find out ·
  • Does the state permit pause (Executive Order 62) apply to this project? 🙋 I'll find out ·
  • When will Guild Ventures apply to the City of Albany for zoning changes? 🙋 I'll find out ·
  • How many megawatts would the data center itself use? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the county tax roll. Guild Ventures LLC owns the 74-acre Kenwood lot at 451 Southern Boulevard. We put the pin there.

    What happened so far

    • May 28, 2026
      Albany County Executive said the city, not the county, would decide on the data center.
    • June 2, 2026
      Residents protested the Kenwood data center plan.
    • Aug 2026
      Developers held a community meeting; about 75 people came. They said they will apply for zoning changes in weeks or months.

    Local votes and rules

    📌 Other

    City council voted 13-0 to support the state's one-year pause on data center construction. Council members say the city has no zoning rules for data centers yet and needs to write them. A data center is proposed at the Kenwood site.

    July 7, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Data center regs advance as opposition to Albany site grows · WAMC · June 3, 2026
    2. Kenwood data center developers try to assuage community concerns · WAMC · Aug 6, 2026
    3. Albany County executive on proposed data center · Spectrum News · May 28, 2026
    4. What does moratorium mean for future of Kenwood data center in Albany? · WAMC · July 17, 2026
    5. NYC developer in hot pursuit of Albany data center · The Real Deal · June 29, 2026
    6. Tax parcel 87.10-1-2.1, 451 Southern Blvd, Albany · NYS GIS Program Office, NYS Tax Parcels (Public) · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.