Fleet / Tract data center off USA Parkway (South Valley)
Also called: South Valley, Fleet Data Centers Storey County campus
Fleet, a company tied to land developer Tract, started building a 2 million square foot data center along USA Parkway in May 2026. It is a $4.6 billion project of about 230 megawatts. The company will not say which big tech firm will use it.
Where things stand: Groundbreaking held in May 2026. Fully leased to an unnamed big tech company.
๐ Latest update (July 2026): NV Energy sued Tract over who decides power costs for its South Valley and Peru Shelf parks.
What we know
- ๐ Wherealong USA Parkway, near the Tahoe-Reno Industrial Center, Storey County
- ๐ข CompanyFleet Data Centers
- ๐๏ธ Owned byTract
- ๐ค Built forunknown (unnamed tech company worth over $3 trillion)
- ๐ณ Size517 acres
- โก Power it needs230 megawatts (about as much as 184,000 homes)
- ๐ Where the power comes fromNV Energy, with an on-site substation. Sierra Club raised concerns about on-site power plants used until grid power is ready.
- ๐ต Cost$4.6 billion
- ๐ท Jobs promised100
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Which tech company will use the South Valley data center? ๐ I'll find out
- How much water will it use per day? ๐ I'll find out
- Will on-site gas or diesel power plants run until the grid connection is ready? ๐ I'll find out
- How much in tax breaks did this project get? ๐ I'll find out
- Is this building inside Tract's South Valley park or its Peru Shelf / Peru Ridge land? Trackers disagree. ๐ I'll find out
What happened so far
- May 19, 2026Fleet raised $4.6 billion in bonds to build a 230 MW data center and substation on a 517-acre site in Storey County.
- May 20, 2026Governor Lombardo joined Fleet and Tract to break ground on a 2 million square foot data center.
- July 2026NV Energy sued Tract over who decides power costs for its South Valley and Peru Shelf parks.
Local votes and rules
โ๏ธ Court case
NV Energy sued data center developer Tract to stop a private arbitration about how much power the utility must supply, and when, to Tract's Peru Shelf and South Valley projects at the Tahoe Reno Industrial Center. NV Energy says these questions belong at the state utility commission so that other customers do not pay the costs. Tract says the contracts require arbitration.
An aerial photo of the area.
Where this comes from
- Gov. Lombardo, construction companies break ground on 2 million sq. ft. data center in Storey Co. ยท KOLO 8 ยท May 20, 2026
- Milbank advises Tract Capital on landmark $4.6B Fleet Data Centers notes offering ยท Milbank ยท May 19, 2026
- Data centers want a closed-door deal. Nevada's electric utility is suing to stop it ยท Straight Arrow News ยท July 30, 2026