ProposedBig (AI-size): 700 megawatts

NTUA energy park with data center (near Morgan Lake, Nenahnezad Chapter)

The Navajo Tribal Utility Authority and a New York investment firm want to build an energy park on about 600 acres near Morgan Lake in San Juan County. A data center using about 700 megawatts would sit on 200 acres, next to factories and power made on site, including gas turbines. A council committee voted against the lease in November 2026; the full Navajo Nation Council has not voted.

👥 Reported, not confirmed yetSourceLast checked: Nov 24, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the San Juan County Commissioners (for land outside city and town limits).

Where things stand: Proposed A Navajo Nation Council committee voted 4-12 against the land lease on Nov. 12, 2026. The full council could still vote, possibly in December. No data center tenant signed.

❓ 4 open questions about it: see below.

Last checked Nov 24, 2026.

🕒 Latest update (Nov 12, 2026): The Naabik'iyati' Committee of the Navajo Nation Council voted 4-12 against the land lease for the energy park. The full council could still vote on it.

What we know

  • 📍 WhereNavajo Nation land just east of Morgan Lake, near the Four Corners power plant and Fruitland, Nenahnezad Chapter (Navajo Nation), San Juan County
  • 🏢 CompanyNavajo Tribal Utility Authority (NTUA) with Lion Point Capital
  • 🌳 Size599 acres
  • ⚡ Power it needs700 megawatts (about as much as 560,000 homes)
  • 🔌 Where the power comes fromPower made on site: solar, batteries and natural gas turbines.
  • 💧 WaterNTUA water rights
  • ❄️ Coolingclosed-loop cooling planned, but not required in the proposal

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • When will the full Navajo Nation Council vote on the lease? 🙋 I'll find out ·
  • Which company would run the data center? 🙋 I'll find out ·
  • How much water would the data center itself use each day, and will there be a cap? 🙋 I'll find out ·
  • Will the gas turbines need an air permit, and from which agency? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Dec 17, 2025
      The Navajo Nation President met with NTUA and Lion Point Capital about a plan that includes a phased data center build-out in the Nenahnezaad and San Juan Chapters.
    • Nov 12, 2026
      The Naabik'iyati' Committee of the Navajo Nation Council voted 4-12 against the land lease for the energy park. The full council could still vote on it.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Navajo Nation Council to weigh data center in San Juan County · Searchlight New Mexico · Nov 19, 2026
    2. President Nygren Meets with NTUA and Lion Point Capital on Clean Energy, Economic Development · Navajo Nation Office of the President and Vice President · Dec 17, 2025