Site Layer 1 gas-powered data center (near Playas and Hachita)
A little-known company plans a gas-powered data center on a ranch in far southern Grant County. Residents and the state Environment Department say too little has been shared. In October 2026 the county adopted a one-year pause on data centers.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Grant County Commissioners (for land outside city and town limits).
Where things stand: Proposed Granite Renewables called the plan conceptual on Oct. 8, 2026. On Oct. 22 the county adopted a one-year pause on data centers, 4-1. No county approval.
- Oct 22, 2026: Grant County: moratorium adopted Source
❓ 6 open questions about it: see below.
Last checked Nov 2, 2026.
🕒 Latest update (Oct 22, 2026): Grant County commissioners voted 4-1 for a one-year pause on building or running data centers while the county considers rules. The developer said the wording was unclear.
What we know
- 📍 WhereRanch land about 4.5 miles northeast of Playas, near Hachita, in southern Grant County, Unincorporated Grant County, Grant County
- 🏢 CompanySite Layer 1 LLC (Granite Renewables)
- ⚡ Power it needs300.8 megawatts (about as much as 240,640 homes)
- 🔌 Where the power comes fromIts own natural gas power plant, near the El Paso Natural Gas pipeline.
- ❄️ Coolingclosed-loop cooling (company says)
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has the air permit application been filed with the Environment Department? 🙋 I'll find out ·
- How much water would it use, and from where? 🙋 I'll find out ·
- Who would use the data center? 🙋 I'll find out ·
- Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
- Will the data center run on gas engines (as the August notice said) or on solar and batteries (as shown to the county on Oct. 8)? 🙋 I'll find out ·
- How big will the data center itself be? 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked for a parcel, address or permit location for this site and did not find one yet.
What happened so far
- Aug 27, 2026A public notice in the Silver City Daily Press said Site Layer 1 will apply for a state air permit for a gas-powered data center.
- Sept 18, 2026The state Environment Secretary wrote that the air permit application would be called incomplete unless the public gets company contacts and a chance to comment.
- Oct 8, 2026Granite Renewables presented the project to the Grant County Commission: a possible 8,000-acre site with 715 MW of solar and 715 MW of batteries. It said water use would be under 25 acre-feet a year but there is no water plan yet.
- Oct 22, 2026Grant County commissioners voted 4-1 for a one-year pause on building or running data centers while the county considers rules. The developer said the wording was unclear.
Local votes and rules
⏸️ Pause on new data centers
Grant County commissioners voted 4-1 for a one-year pause on building, expanding or running any data center or its supporting equipment while the county decides on rules. It followed the Site Layer 1 proposal near Hachita. The developer said the wording was unclear.
⏸️ Pause on new data centers
County commissioners approved a notice that they will consider a one-year pause on data centers, modeled on Socorro County's. One commissioner voted no, citing property rights. The pause itself was set to be weighed at the Oct. 8, 2026 meeting. It follows the Site Layer 1 plan near Hachita and Playas.
Drag the slider to compare the land before and now.
Where this comes from
- Grant County residents raise alarm over secretive proposed data center · Searchlight New Mexico · Sept 9, 2026
- In Silver City, rapid community response to local data center proposal · Albuquerque Journal · Sept 2026
- Air facilities map service (searched for this applicant) · New Mexico Environment Department, Air Quality Bureau · Oct 8, 2026
- Grant County data center proposal leaves key details unanswered · Albuquerque Journal · Oct 9, 2026
- Grant County enacts New Mexico's latest data center moratorium · Albuquerque Journal · Oct 22, 2026