Approved, not built yetBig (AI-size): 194 acres

QTS data center campus on Princeton-Hightstown Road

Also called: QTS East Windsor 1, former McGraw-Hill site

QTS, owned by Blackstone, runs a data center on the old McGraw-Hill campus in East Windsor. It wants to add a second, larger building. Residents asked about higher power bills at packed planning board meetings.

👥 Reported, not confirmed yetSourceLast checked: Oct 7, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Committee or Council of East Windsor Township.

Where things stand: Approved, not built yet First building opened in 2025. A second building was reported approved by the planning board in May 2026.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (May 2026): Planning board approved a second data center building (about $600 million), with conditions on cooling and paying for road and utility upgrades.

What we know

  • 📍 Where159 Princeton-Hightstown Road (former McGraw-Hill campus), East Windsor, Mercer County
  • 🏢 CompanyQTS Data Centers
  • 🏛️ Owned byBlackstone
  • 🌳 Size194 acres
  • 🔌 Where the power comes fromPower grid; the campus also has a 50-acre solar field (tracker data).
  • ❄️ CoolingClosed-loop cooling for the second building (reported)
  • 💵 Cost$600 million

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Did the planning board approve the second building, and on what date? We only found this on a data center tracker. 🙋 I'll find out ·
  • How much power (MW) will the full campus use? 🙋 I'll find out ·
  • How much water will the campus use per day? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Nov 19, 2024
      Topping-out ceremony for the first building.
    • April 2025
      First phase finished, per the township.
    • May 2026
      Planning board approved a second data center building (about $600 million), with conditions on cooling and paying for road and utility upgrades.

    Local votes and rules

    ⏸️ Pause on new data centers

    East Windsor posted Ordinance 2026-06, which would pause new data centers through Dec. 31, 2027 while the state writes rules. It removes computer and data storage centers as allowed uses in the R-O, R-O2 and I-O zones. The posted copy has no adoption date, so we could not confirm it passed. QTS already runs a data center in the township.

    2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. QTS topping-out ceremony · East Windsor Township · Nov 2024
    2. QTS: East Windsor 1 DC2 · Baxtel · 2026