Built & running
Meta Sarpy data center campus (Papillion and Springfield)
Also called: Facebook Sarpy Data Center
Meta (Facebook) runs a large data center campus in Sarpy County. It started in Papillion and grew into Springfield, with nine buildings and about 4 million square feet planned. Meta says its power comes from wind farms.
Where things stand: Running since about 2019 and grown to nine buildings.
๐ Latest update (July 2022): Meta announced a ninth building, bringing the campus to about 4 million square feet and more than $1.5 billion.
What we know
- ๐ Wherealong Nebraska Highway 50, south of Omaha, with buildings in the Papillion and Springfield areas, Papillion, Sarpy County
- ๐ข CompanyMeta
- ๐๏ธ Owned byMeta Platforms
- ๐ค Built forMeta
- ๐ Where the power comes fromOmaha Public Power District (OPPD); Meta says it buys wind power from northeast Nebraska and Kansas
- ๐ต Cost$1.5 billion
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much water does the Meta campus use per day? ๐ I'll find out
- Are more buildings planned after the ninth? ๐ I'll find out
- Are all nine buildings running now? ๐ I'll find out
What happened so far
- 2017Construction started on Facebook's Sarpy County data center.
- July 2022Meta announced a ninth building, bringing the campus to about 4 million square feet and more than $1.5 billion.
๐ฐ๏ธ See it from above
An aerial photo of the area.
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Meta, Facebook's parent company, expands data center under construction near Omaha again ยท KMTV 3 News Now ยท July 2022