Sequitor Edge data center in Tech oNE Crossing (Kearney)

Sequitor Edge plans a smaller 40,000-square-foot data center on 16 acres in Kearney's Tech oNE Crossing park. It would offer computer space for local businesses, health care and farm tech. Opening is planned for 2027.

๐Ÿ‘ฅ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: Reported that Kearney approved selling 16 acres for the site; opening planned for 2027.

What we know

  • ๐Ÿ“ WhereTech One Boulevard, Tech oNE Crossing park, Kearney, Kearney, Buffalo County
  • ๐Ÿข CompanySequitor Edge
  • ๐Ÿ‘ค Built forSequitor Edge (colocation and AI services)
  • ๐ŸŒณ Size16 acres
  • ๐Ÿ”Œ Where the power comes fromNebraska Public Power District (NPPD) substations

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

Local votes and rules

๐Ÿ“œ Data center rules

The city council voted 5-0 for Kearney's first data center zoning rules instead of a pause. Data centers need a conditional use permit, water and wastewater studies, and must meet a 55-decibel average noise cap.

Sept 8, 2026

โœ… Approved

The city council voted 5-0 to approve a conditional use permit for the Tech One Crossing data center campus. It replaces a bitcoin mine and could use 368 megawatts when fully built.

Sept 8, 2026
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Sequitor Edge: Kearney, NE ยท Baxtel
  2. Sequitor Edge to build data center on 16-acre land parcel in Kearney, Nebraska ยท DatacenterDynamics

See something wrong? Tell us and we'll fix it.