Stark Power data center and gas plant north of Mandan
Also called: Sagebrush Infrastructure Partners
A company plans a data center with its own gas power plant just north of Mandan. It is an early plan with no application yet. Neighbors worry about noise near schools.
Where things stand: Open house held Aug. 20, 2026. No zoning application yet; city and county are still writing data center rules.
π Latest update (Aug 20, 2026): Stark Power held its first public open house on the project.
What we know
- π Wherenorth of Mandan, near Mandan schools, Mandan, Morton County
- π’ CompanyStark Power (buying Sagebrush Infrastructure Partners LLC)
- π Where the power comes fromA natural gas power plant on the campus (company plan)
- π€ Secret deal (NDA)No
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How big would the data center be, in acres and megawatts? π I'll find out
- Is the whole site inside Mandan city limits? π I'll find out
- How much water would it use? π I'll find out
- Where exactly is the site? A parcel number, address or agenda link helps. π I'll find out
π What we checked
- Oct 8, 2026: We checked news reports: the site is north of I-94 between Highway 1806 and Old Red Trail, near Mandan schools. No parcel list is public, so we did not place an exact pin.
What happened so far
- March 2026Sagebrush Infrastructure Partners signed options to buy land from three Morton County landowners.
- Aug 20, 2026Stark Power held its first public open house on the project.
Local votes and rules
π³οΈ Public vote
On Sept. 22, 2026, residents turned in a petition (706 signatures; 435 needed) for a city vote to limit any data center in Mandan to 25 megawatts. The city must check the signatures. The mayor said it likely misses the Nov. 3 ballot and would go to a later special election.
π Data center rules
Mandan's planning and zoning board voted unanimously to recommend a data center ordinance, after adding six changes, including tighter noise limits, more monitoring and coolants without PFAS (forever chemicals). It now goes to the City Commission. We did not find a final vote.
βΈοΈ Pause on new data centers
The county paused data centers and crypto mines until it adopted siting and performance rules. Those rules were adopted on Sept. 10, 2026. The county has not said publicly if the pause has formally ended.
Drag the slider to compare the land before and now.
Where this comes from
- Stark Power hosts first public event on proposed Mandan data center project Β· KFYR / Valley News Live Β· Aug 20, 2026
- Data center developer secures options to buy land from three Morton County landowners Β· KX News Β· 2026
- Packed meeting on data center draft ordinance; Possible data center coming to Mandan Β· KFYR-TV Β· July 23, 2026
- Proposed data center near Mandan draws concern over school proximity Β· KFYR-TV Β· Aug 21, 2026