πŸ“£ Report Something
Proposed

River Run Energy Center data center campus (Mercer County)

Also called: River Run Energy Center

Power companies want to build a large gas power plant with a data center campus of several gigawatts in Mercer County. The county paused all data center projects for one year in March 2026.

βœ” ConfirmedSourceLast checked: Oct 2026

Where things stand: Gas plant plus data center campus announced Dec. 2025. Mercer County paused data centers for one year in March 2026.

πŸ•’ Latest update (March 30, 2026): Basin Electric and NextEra held a public open house on the project.

What we know

  • πŸ“ WhereUnincorporated Mercer County, Mercer County
  • 🏒 CompanyNextEra Energy Resources and Basin Electric Power Cooperative
  • 🌳 Size530 acres
  • πŸ”Œ Where the power comes fromA new 1,450 MW natural gas power plant next to the campus
  • πŸ’΅ Cost$18 billion
  • πŸ‘· Jobs promised230

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

πŸ”Ž What we checked

  • Oct 8, 2026: We checked NextEra's project page: the gas plant would sit next to the Leland Olds substation off Highway 200, but the data center land (up to about 1,500 acres of options) is not public.

What happened so far

  • Dec 2025
    Basin Electric and NextEra announced the River Run Energy Center plan.
  • March 3, 2026
    Mercer County Commission voted 3-2 to pause data center development for one year.
  • March 30, 2026
    Basin Electric and NextEra held a public open house on the project.

Local votes and rules

⏸️ Pause on new data centers

County commissioners voted 3-2 to pause data center applications for one year, so staff can write rules. It came as Basin Electric and NextEra looked at the county for a gas plant and data center campus. The county had no application at the time.

March 3, 2026
πŸ›°οΈ See it from above

Drag the slider to compare the land before and now.

20182025
We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Data center concerns rise in 2nd western North Dakota county as NextEra, Basin eye project Β· Grand Forks Herald Β· March 5, 2026
  2. Basin Electric and NextEra Energy Resources hold an open house for proposed River Run Energy Center Β· Basin Electric Β· April 9, 2026
  3. Mercer County issues moratorium on data centers Β· KFYR-TV Β· March 4, 2026
  4. River Run Energy Center FAQ Β· NextEra Energy Resources Β· 2026

See something wrong? Tell us and we'll fix it.