Natelli site on U.S. 158 Business near Henderson
The developer behind the dropped Apex plan got a 40-acre rezoning near Henderson in April 2026. Local news describes plans for about 4 million square feet and around 350 jobs. Many residents oppose it if it becomes a data center.
Where things stand: County commissioners rezoned 40 acres to light industrial on April 20, 2026. The developer has not confirmed it will be a data center.
π Latest update (April 20, 2026): County commissioners voted at a special meeting to rezone 40 acres to light industrial.
What we know
- π WhereU.S. 158 Business between Pine Meadow Trail and Horseshoe Bend Road, next to the Triangle North Vance business park, across I-85 from Vance-Granville Community College, Vance County, Vance County
- π’ CompanyNatelli Investments LLC
- π³ Size40 acres
- π· Jobs promised350
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Will this be a data center? The developer has not confirmed it. π I'll find out
- How much power and water would it need? π I'll find out
What happened so far
- April 20, 2026County commissioners voted at a special meeting to rezone 40 acres to light industrial.
Local votes and rules
πΊοΈ Zoning change
Vance County commissioners rezoned 40 acres along U.S. 158 near Henderson to light industrial for Natelli Investments, at a special meeting. Residents later raised concerns about how open the process was.
An aerial photo of the area.
Where this comes from
- Central North Carolina data center plans Β· WRAL Β· April 2026
- Data center projects progressing Β· Henderson Daily Dispatch Β· June 5, 2026
See something wrong? Tell us and we'll fix it.