Stopped or cancelledBig (AI-size): 300 megawatts

Tarboro data center (Energy Storage Solutions)

Energy Storage Solutions wanted to build a $6.4 billion, 300-megawatt data center on 52 acres of heavy industrial land in Tarboro. The Town Council said no in September 2025. The company sued, but in July 2026 it said it would not build there.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

Where things stand: Stopped or cancelled Town Council denied the permit in September 2025. In July 2026 the company said it will not build there and expects to drop its lawsuit.

❓ 1 open question about it: see below.

📣 See work going on anyway? Tell us

Last checked Oct 8, 2026.

🕒 Latest update (July 2026): The company said it reached a settlement with the town, expects to drop the lawsuit, and will not build in Tarboro.

What we know

  • 📍 WhereNear Anaconda Road and McNair Road, Tarboro, Tarboro, Edgecombe County
  • 🏢 CompanyEnergy Storage Solutions LLC
  • 🌳 Size52 acres
  • ⚡ Power it needs300 megawatts (about as much as 240,000 homes)
  • 🔌 Where the power comes fromOn-site power generation yards and battery storage were planned.
  • 💧 Water500,000 gallons a day
  • 💵 Cost$6.4 billion
  • 👷 Jobs promised500

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Has the lawsuit against the Town of Tarboro been formally dropped, and what are the settlement terms? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Sept 2025
      Tarboro Town Council voted to deny a special use permit for the data center.
    • Nov 2025
      The developer appealed the denial to Edgecombe County Superior Court.
    • July 2026
      The company said it reached a settlement with the town, expects to drop the lawsuit, and will not build in Tarboro.

    Local votes and rules

    ✋ Turned down

    Tarboro Town Council voted 6-1 to deny a special use permit for a 50-acre data center by Energy Storage Solutions, citing environmental effects and neighbors' objections. The company sued, then said in July 2026 it reached a settlement and will not build there.

    Sept 8, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Developer Forges Ahead With $38B in North Carolina Data Center Builds · Data Center Knowledge · Nov 5, 2025
    2. Company that eyed land for data center withdraws its offer · Rocky Mount Telegram · July 14, 2026
    3. $20B North Carolina Data Center Canceled Amid Moratorium Debate · Bisnow · July 8, 2026
    4. Parcels along Anaconda Rd and McNair Rd, Tarboro (used to place the road crossing) · NC OneMap statewide parcels (county tax records) · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.