Approved, not built yet

Project Delta data center campus along the Dan River

Also called: Project Delta

A developer wants to build a huge data center campus on about 1,800 acres of farmland along the Dan River. The first approval was thrown out after a lawsuit over public notice. Commissioners approved it again 3-2 in September 2026 with stricter rules on noise, power and water.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Commissioners approved the new rezoning 3-2 in September 2026, after a court voided the first approval. More lawsuits are possible.

πŸ•’ Latest update (Sept 2026): Commissioners approved the new rezoning 3-2 with stricter rules on noise, power and water.

What we know

  • πŸ“ WhereAbout 1,800 acres of farmland along the Dan River near the Virginia line, in the Walnut Cove area, Stokes County, Stokes County
  • 🏒 CompanyEngineered Land Solutions (ELS)
  • 🌳 Size1,848 acres
  • πŸ”Œ Where the power comes fromA new substation just for the campus; on-site power generation is possible.
  • πŸ—Ό New power linesYes
  • ❄️ Coolingclosed-loop cooling (developer says)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Jan 12, 2026
    County commissioners approved the rezoning 3-2, against the planning board's advice.
  • March 12, 2026
    Community groups sued to block the rezoning.
  • July 2026
    ELS filed a new rezoning application.
  • July 13, 2026
    Commissioners allowed data centers in heavy industrial conditional zones countywide and rejected a moratorium.
  • Aug 2026
    Planning board voted 5-2 to recommend denial again; a court voided the January rezoning.
  • Sept 2026
    Commissioners approved the new rezoning 3-2 with stricter rules on noise, power and water.

Local votes and rules

πŸ—ΊοΈ Zoning change

Stokes County commissioners voted 3-2 to rezone about 1,800 acres for the Project Delta data center, after a January approval was voided. The developer added stricter limits on noise, power and water. Opponents' lawyers said more legal action is possible.

Sept 14, 2026

πŸ“Œ Other

Stokes County commissioners voted down a six-month data center pause that the planning board had recommended. The same night they changed county rules to allow data centers in heavy industrial conditional zones countywide.

July 13, 2026

βš–οΈ Court case

Community groups and residents, represented by the Southern Coalition for Social Justice and the Southern Environmental Law Center, sued over the January 2026 Project Delta rezoning and a countywide rule change. The January rezoning was later voided, and the developer reapplied.

March 12, 2026
πŸ›°οΈ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. What is going on with data centers in Stokes County, North Carolina? Β· Southern Coalition for Social Justice Β· 2026
  2. Inside Stokes County's latest vote on the Project Delta data center Β· WUNC Β· Sept 15, 2026
  3. Planning board again recommends denial of Stokes data center Β· WFAE Β· Aug 14, 2026
  4. Stokes County proposed data center creates backlash Β· Spectrum News Β· Jan 12, 2026
  5. Proposal filed for 1,800-acre data center campus outside Greensboro, North Carolina Β· Baxtel Β· Jan 10, 2026