Approved, not built yetBig (AI-size): 330 acres

Compass Datacenters campus on Stamey Farm Road

Compass Datacenters plans five data center buildings of about 270,000 square feet each on about 330 acres near I-40 in Statesville. The city approved the rezoning 8-0 in 2025. Plans show about 40 backup generators per building.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Statesville City.

Where things stand: Approved, not built yet City Council approved the rezoning in September 2025. Statesville's 2026 data center pause exempts this project.

❓ 3 open questions about it: see below.

Last checked Nov 17, 2026.

🕒 Latest update (Sept 15, 2026): Statesville adopted a 180-day data center pause that exempts the Compass project.

What we know

  • 📍 Where255 Stamey Farm Road and nearby parcels, between I-40 and Hickory Highway, west Statesville, Statesville, Iredell County
  • 🏢 CompanyCompass Datacenters
  • 🌳 Size330 acres
  • 🔌 Where the power comes fromDuke Energy; a nearby substation
  • ❄️ Coolingclosed-loop hybrid cooling that recycles water (company says)
  • 🛢️ Diesel generators200
  • 👷 Jobs promised200

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: county tax records show Compass Datacenters owns about 329 acres on Stamey Farm Road. The pin is the centre of that land.

    What happened so far

    • Sept 15, 2025
      Statesville City Council voted unanimously to approve the rezoning; final vote set for Oct. 1.
    • Oct 6, 2025
      Statesville City Council gave final approval to the rezoning on second reading, on the consent agenda.
    • Sept 15, 2026
      Statesville adopted a 180-day data center pause that exempts the Compass project.

    Local votes and rules

    ⏸️ Pause on new data centers

    Statesville City Council unanimously passed a 180-day pause on new data center applications in city limits. The Compass data center on Stamey Farm Road, approved earlier, is exempt.

    Sept 14, 2026

    ✅ Approved

    Statesville City Council gave final approval (second reading) to the rezoning for the Compass data center campus on Stamey Farm Road. It passed on the consent agenda, with about 30 people speaking against the project. Council also set an Oct. 20, 2025 hearing on bringing the land into city limits.

    Oct 6, 2025

    🗺️ Zoning change

    Statesville City Council unanimously advanced a rezoning of 365 acres near Stamey Farm Road and I-40 for a five-building Compass Data Centers campus, with a final vote set for Oct. 1, 2025.

    Sept 15, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something