Approved, not built yetBig (AI-size): 430 acres

PointOne / CyrusOne data center on Lower Moncure Road

PointOne wants to build a 90-megawatt data center run by CyrusOne on Lower Moncure Road. The first phase is a 300,000-square-foot building on 56 acres of a 430-acre site. CyrusOne projects more than $900 million in investment for that phase; the building permit values the building alone at about $185 million. Residents say the land was rezoned as a 'light industrial business park' without saying it was for a data center.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Lee County Board of Commissioners (for land outside city and town limits).

Where things stand: Approved, not built yet Building permit issued Sept. 25, 2026. The county says the project is protected (vested) under state law, so a later pause cannot stop it. Construction expected to start this fall.

  • Oct 13, 2026: Our records now list PointOne / CyrusOne data center on Lower Moncure Road as approved Source

❓ 2 open questions about it: see below.

Last checked Nov 2, 2026.

🕒 Latest update (Oct 1, 2026): Lee County said the project is vested under state law, will not face a new vote by commissioners, and cannot be stopped by a later pause or rule change. The county said it gave no incentives.

What we know

  • 📍 Where4015 Lower Moncure Road, northern Lee County (Sanford mailing address), Lee County, Lee County
  • 🏢 CompanyPointOne Data Centers (with Helix Ventures)
  • 👤 Built forCyrusOne (operator)
  • 🌳 Size430 acres
  • ⚡ Power it needs90 megawatts (about as much as 72,000 homes)
  • 🔌 Where the power comes fromCentral Electric Membership Corporation substation. Local reporting also mentions links to a planned natural gas pipeline.
  • ❄️ CoolingClosed-loop cooling; about 250,000 gallons trucked in once and reused, per CyrusOne
  • 💵 Cost$900 million
  • 👷 Jobs promised40

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will the data center use the planned gas pipeline for power? 🙋 I'll find out ·
  • How loud will the site be at night for nearby homes? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • March 17, 2026
      Residents asked Lee County for a data center pause after learning a developer was looking at a site near Sanford.
    • June 2026
      PointOne filed a permit application for a 300,000-square-foot data center on 56 acres, the first phase of a 430-acre site.
    • July 13, 2026
      About 150 residents spoke against the plan at a commissioners meeting.
    • Aug 18, 2026
      Commissioners rejected two attempts to pause the project, including a 90-day moratorium motion.
    • Sept 25, 2026
      The Sanford-Lee County planning department issued a building permit for a data center of more than 300,000 square feet at 4015 Lower Moncure Road. The permit values the building at about $185 million and is good until March 24, 2027.
    • Oct 1, 2026
      Lee County said the project is vested under state law, will not face a new vote by commissioners, and cannot be stopped by a later pause or rule change. The county said it gave no incentives.

    Local votes and rules

    📌 Other

    A Lee County commissioner proposed a 90-day pause on new data centers, but withdrew it without a vote after the county attorney said state notice and hearing rules were not followed. The chair instead offered a resolution asking the state to pass data center laws.

    Aug 17, 2026

    📜 Data center rules

    Lee County added data center rules to its development code, by a 5-1 vote. Developers must meet with staff first, do a noise study, and show they have water, sewer and power.

    April 20, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Lee County residents ask for a data center moratorium · WUNC · March 17, 2026
    2. Data center proposed in northern Lee County · The Rant · June 8, 2026
    3. Data Center Developer Seeks To Build 300K SF Facility Near Raleigh · Bisnow · June 2026
    4. Data center opponents speak out before commissioners · The Rant · July 14, 2026
    5. Commissioners reject attempts to pause data center project · The Rant · Aug 18, 2026
    6. Planning department issues data center permit · The Rant (Sanford) · Sept 29, 2026
    7. County says data center project will proceed, releases project timeline · The Rant (Sanford) · Oct 1, 2026
    8. Census geocoder: 4015 Lower Moncure Rd, Sanford, NC · U.S. Census Bureau · Oct 13, 2026
    9. Lee County, North Carolina · CyrusOne · 2026

    See something wrong? Tell us and we'll fix it.