PointOne / CyrusOne data center on Lower Moncure Road
PointOne wants to build a 90-megawatt data center run by CyrusOne on Lower Moncure Road. The first phase is a 300,000-square-foot building on 56 acres of a 430-acre site. CyrusOne projects more than $900 million in investment for that phase; the building permit values the building alone at about $185 million. Residents say the land was rezoned as a 'light industrial business park' without saying it was for a data center.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Lee County Board of Commissioners (for land outside city and town limits).
Where things stand: Approved, not built yet Building permit issued Sept. 25, 2026. The county says the project is protected (vested) under state law, so a later pause cannot stop it. Construction expected to start this fall.
- Oct 13, 2026: Our records now list PointOne / CyrusOne data center on Lower Moncure Road as approved Source
❓ 2 open questions about it: see below.
Last checked Nov 2, 2026.
🕒 Latest update (Oct 1, 2026): Lee County said the project is vested under state law, will not face a new vote by commissioners, and cannot be stopped by a later pause or rule change. The county said it gave no incentives.
What we know
- 📍 Where4015 Lower Moncure Road, northern Lee County (Sanford mailing address), Lee County, Lee County
- 🏢 CompanyPointOne Data Centers (with Helix Ventures)
- 👤 Built forCyrusOne (operator)
- 🌳 Size430 acres
- ⚡ Power it needs90 megawatts (about as much as 72,000 homes)
- 🔌 Where the power comes fromCentral Electric Membership Corporation substation. Local reporting also mentions links to a planned natural gas pipeline.
- ❄️ CoolingClosed-loop cooling; about 250,000 gallons trucked in once and reused, per CyrusOne
- 💵 Cost$900 million
- 👷 Jobs promised40
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Will the data center use the planned gas pipeline for power? 🙋 I'll find out ·
- How loud will the site be at night for nearby homes? 🙋 I'll find out ·
What happened so far
- March 17, 2026Residents asked Lee County for a data center pause after learning a developer was looking at a site near Sanford.
- June 2026PointOne filed a permit application for a 300,000-square-foot data center on 56 acres, the first phase of a 430-acre site.
- July 13, 2026About 150 residents spoke against the plan at a commissioners meeting.
- Aug 18, 2026Commissioners rejected two attempts to pause the project, including a 90-day moratorium motion.
- Sept 25, 2026The Sanford-Lee County planning department issued a building permit for a data center of more than 300,000 square feet at 4015 Lower Moncure Road. The permit values the building at about $185 million and is good until March 24, 2027.
- Oct 1, 2026Lee County said the project is vested under state law, will not face a new vote by commissioners, and cannot be stopped by a later pause or rule change. The county said it gave no incentives.
Local votes and rules
📌 Other
A Lee County commissioner proposed a 90-day pause on new data centers, but withdrew it without a vote after the county attorney said state notice and hearing rules were not followed. The chair instead offered a resolution asking the state to pass data center laws.
📜 Data center rules
Lee County added data center rules to its development code, by a 5-1 vote. Developers must meet with staff first, do a noise study, and show they have water, sewer and power.
Drag the slider to compare the land before and now.
Where this comes from
- Lee County residents ask for a data center moratorium · WUNC · March 17, 2026
- Data center proposed in northern Lee County · The Rant · June 8, 2026
- Data Center Developer Seeks To Build 300K SF Facility Near Raleigh · Bisnow · June 2026
- Data center opponents speak out before commissioners · The Rant · July 14, 2026
- Commissioners reject attempts to pause data center project · The Rant · Aug 18, 2026
- Planning department issues data center permit · The Rant (Sanford) · Sept 29, 2026
- County says data center project will proceed, releases project timeline · The Rant (Sanford) · Oct 1, 2026
- Census geocoder: 4015 Lower Moncure Rd, Sanford, NC · U.S. Census Bureau · Oct 13, 2026
- Lee County, North Carolina · CyrusOne · 2026
See something wrong? Tell us and we'll fix it.