Status unclearBig (AI-size): 300 megawatts

HB2K AI data center campus (Kings Mountain)

Also called: HB2K Data Center Campus

A Nevada developer says its land in Kings Mountain is approved for an AI data center campus of 150 to 300 megawatts. It sued the city over utilities. No construction has been seen.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Kings Mountain City.

Where things stand: Status unclear The developer says the land is zoned for an AI data center and sued the city over utilities. Kings Mountain paused new data centers in Feb. 2026; it is unclear if the pause applies.

❓ 3 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Feb 2026): Kings Mountain City Council approved a six-month data center moratorium 5-2.

What we know

  • 📍 Where166 Gage Road, next to Duke Energy land, south Kings Mountain, Kings Mountain, Cleveland County
  • 🏢 CompanyHB2K LLC (Honey Badger Development)
  • ⚡ Power it needs300 megawatts (about as much as 240,000 homes)
  • 🔌 Where the power comes fromDeveloper claims a 150-300 MW power path

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Where exactly is the site, and how many acres? 🙋 I'll find out ·
  • Does the city's moratorium apply to this project? 🙋 I'll find out ·
  • What is the status of the lawsuit against the city? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: county tax records show HB2K LLC owns about 78 acres at 166 Gage Road. The pin is the centre of that land.

    What happened so far

    • 2026
      HB2K sued the city over utility service for the site.
    • Feb 2026
      Kings Mountain City Council approved a six-month data center moratorium 5-2.

    Local votes and rules

    ⏸️ Pause on new data centers

    Kings Mountain City Council voted 5-2 for a 182-day pause on data centers while staff study design, utilities and noise rules. In summer 2026 the planning board recommended a 12-month extension; the council delayed its decision.

    Feb 24, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Couple regrets selling family land for data center project · WSPA / NewsNation · 2026
    2. Kings Mountain residents share concerns as another data center is proposed · WBTV · Feb 24, 2026
    3. Parcel 49416, 166 Gage Rd, owned by HB2K LLC (about 78 acres, Reno NV mailing address) · NC OneMap statewide parcels (county tax records) · Oct 8, 2026