Project Iron Spur hyperscale data center (Rural Hall area, denied)

Also called: Project Iron Spur

The Drox Group wanted to build a $3 billion hyperscale data center on 129 acres near Rural Hall. After months of opposition, county commissioners voted it down 5-2 in July 2026.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Forsyth County commissioners voted 5-2 against the rezoning in July 2026.

๐Ÿ•’ Latest update (July 30, 2026): County commissioners voted 5-2 to deny the rezoning.

What we know

  • ๐Ÿ“ WhereAbout 129 acres across from Rural Hall Town Hall, on county land, Forsyth County, Forsyth County
  • ๐Ÿข CompanyThe Drox Group
  • ๐ŸŒณ Size129 acres
  • ๐Ÿ’ต Cost$3 billion

What happened so far

  • June 11, 2026
    The planning board recommended denying the rezoning.
  • July 30, 2026
    County commissioners voted 5-2 to deny the rezoning.

Local votes and rules

โœ‹ Turned down

Forsyth County commissioners voted 5-2 against rezoning about 129 acres in Rural Hall for the Project Iron Spur data center campus. The planning board had also recommended denial.

July 30, 2026

๐Ÿ“Œ Other

Rural Hall Town Council unanimously passed a resolution against rezoning land for the Project Iron Spur data center. The mayor said the town has no legal power to pass its own pause; the county decides the rezoning.

April 2026
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Forsyth commission votes down Rural Hall data center proposal ยท WUNC (WFDD) ยท July 30, 2026
  2. Planning board recommends denying rezoning for proposed Rural Hall data center ยท WUNC (WFDD) ยท June 11, 2026