Possible data center site at 1316 NC 61 South
Burlington rezoned 40 acres next to Lake Mackintosh for industry in 2025. The developer said he hopes to bring a small data center but had no tenant. Building near the lake must follow water-protection rules.
Where things stand: City Council rezoned the land to industrial in June 2025. The developer hopes to attract a small data center but has no tenant.
π Latest update (June 17, 2025): Burlington City Council approved medium industrial zoning 5-0.
What we know
- π Where1316 NC 61 South, west of Lake Mackintosh, eastern Guilford County, Burlington, Guilford County
- π’ CompanyA Georgia-based developer (not a company name in reports)
- π³ Size40 acres
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has any data center company signed up for the site? π I'll find out
- Would building there affect Lake Mackintosh, a drinking water lake? π I'll find out
What happened so far
- April 2025Planning board recommended rezoning 6-0 after the developer said he hoped to bring a data center.
- June 17, 2025Burlington City Council approved medium industrial zoning 5-0.
Local votes and rules
βΈοΈ Pause on new data centers
Guilford County's commission chair said he would move to start a 180-day pause on data centers. The county's rules do not define a data center yet, and staff suggested adding rules. No project is pending.
πΊοΈ Zoning change
Burlington City Council voted 5-0 to rezone 40 lakefront acres at 1316 NC 61 South to medium industrial. The developer said he hopes to attract a data center; none is signed.
An aerial photo of the area.
Where this comes from
- Burlington city council approves industrial use on lakefront tract in eastern Guilford County Β· The Alamance News Β· June 19, 2025