DeSoto Innovation District (with possible data center) in Olive Branch
A nearly 600-acre development in Olive Branch listed a data center as a possible use. After an uproar online, the city Planning Commission denied it in June 2026. The city later passed stricter data center rules.
Where things stand: The Olive Branch Planning Commission denied the project in June 2026.
๐ Latest update (June 2026): Olive Branch Planning Commission denied the nearly 600-acre project after papers showed a data center as an allowed use.
What we know
- ๐ WhereChurch Road area, Olive Branch, DeSoto County
- ๐ณ Size600 acres
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who is the developer? ๐ I'll find out
- Will the developer appeal to the Board of Aldermen or come back with a new plan? ๐ I'll find out
What happened so far
- June 2026Olive Branch Planning Commission denied the nearly 600-acre project after papers showed a data center as an allowed use.
Local votes and rules
๐ Data center rules
Olive Branch added data center rules to its zoning code in August 2026, effective right away. Data centers now need a conditional use permit, with public hearings, instead of being allowed by right in industrial areas. The rules limit noise and how close data centers can be to homes.
โ Turned down
The Planning Commission turned down the nearly 600-acre DeSoto Innovation District after papers showed a data center as an allowed use. It also talked about stricter rules for future data center requests.
An aerial photo of the area.
Where this comes from
- Olive Branch Planning Commission denies new project ยท Daily Memphian ยท June 2026
See something wrong? Tell us and we'll fix it.