DeSoto Innovation District (with possible data center) in Olive Branch
A nearly 600-acre development in Olive Branch listed a data center as a possible use. After an uproar online, the city Planning Commission denied it in June 2026. The city later passed stricter data center rules.
What happens next?
Where things stand: Stopped or cancelled The Olive Branch Planning Commission denied the project in June 2026.
❓ 3 open questions about it: see below.
📣 See work going on anyway? Tell us
Last checked Oct 8, 2026.
🕒 Latest update (June 2026): Olive Branch Planning Commission denied the nearly 600-acre project after papers showed a data center as an allowed use.
What we know
- 📍 WhereChurch Road area, Olive Branch, DeSoto County
- 🌳 Size600 acres
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who is the developer? 🙋 I'll find out ·
- Will the developer appeal to the Board of Aldermen or come back with a new plan? 🙋 I'll find out ·
- Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
What happened so far
- June 2026Olive Branch Planning Commission denied the nearly 600-acre project after papers showed a data center as an allowed use.
Local votes and rules
📜 Data center rules
Olive Branch added data center rules to its zoning code in August 2026, effective right away. Data centers now need a conditional use permit, with public hearings, instead of being allowed by right in industrial areas. The rules limit noise and how close data centers can be to homes.
✋ Turned down
The Planning Commission turned down the nearly 600-acre DeSoto Innovation District after papers showed a data center as an allowed use. It also talked about stricter rules for future data center requests.
Drag the slider to compare the land before and now.
Where this comes from
- Olive Branch Planning Commission denies new project · Daily Memphian · June 2026
See something wrong? Tell us and we'll fix it.