Stopped or cancelledBig (AI-size): 600 acres

DeSoto Innovation District (with possible data center) in Olive Branch

A nearly 600-acre development in Olive Branch listed a data center as a possible use. After an uproar online, the city Planning Commission denied it in June 2026. The city later passed stricter data center rules.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

Where things stand: Stopped or cancelled The Olive Branch Planning Commission denied the project in June 2026.

❓ 3 open questions about it: see below.

📣 See work going on anyway? Tell us

Last checked Oct 8, 2026.

🕒 Latest update (June 2026): Olive Branch Planning Commission denied the nearly 600-acre project after papers showed a data center as an allowed use.

What we know

  • 📍 WhereChurch Road area, Olive Branch, DeSoto County
  • 🌳 Size600 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who is the developer? 🙋 I'll find out ·
  • Will the developer appeal to the Board of Aldermen or come back with a new plan? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • June 2026
      Olive Branch Planning Commission denied the nearly 600-acre project after papers showed a data center as an allowed use.

    Local votes and rules

    📜 Data center rules

    Olive Branch added data center rules to its zoning code in August 2026, effective right away. Data centers now need a conditional use permit, with public hearings, instead of being allowed by right in industrial areas. The rules limit noise and how close data centers can be to homes.

    Aug 2026

    ✋ Turned down

    The Planning Commission turned down the nearly 600-acre DeSoto Innovation District after papers showed a data center as an allowed use. It also talked about stricter rules for future data center requests.

    June 9, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Olive Branch Planning Commission denies new project · Daily Memphian · June 2026

    See something wrong? Tell us and we'll fix it.