๐Ÿ“ฃ Report Something
Built & running

Amazon Web Services data center campus at the Madison County Mega Site near Canton

Also called: AWS Madison Mega Site, AWS Canton campus

Amazon runs five large data center buildings at the Madison County Mega Site near Canton, part of a $10 billion plan first announced in 2024. In 2026 the county and Amazon disagreed over how much the buildings are worth for taxes. Amazon says this site cools with recycled wastewater.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Five buildings are running; Madison County taxed each one for 2026.

๐Ÿ•’ Latest update (Aug 17, 2026): Madison County supervisors set a value of about $292 million on each of the five Canton buildings; Amazon had argued for about $70 million each.

What we know

  • ๐Ÿ“ WhereMadison County Mega Site, outside Canton, Unincorporated Madison County, Madison County
  • ๐Ÿข CompanyAmazon Web Services
  • ๐Ÿ›๏ธ Owned byAmazon
  • ๐Ÿ‘ค Built forAmazon Web Services
  • ๐Ÿ”Œ Where the power comes fromEntergy Mississippi
  • ๐Ÿ’ง WaterRecycled wastewater (Amazon says about 83 million gallons a year at Canton)
  • โ„๏ธ CoolingMostly air cooling; Amazon says it uses water for cooling only on the hottest days.
  • ๐Ÿ’ธ Tax breaksFee-in-lieu-of-taxes deal with Madison County; payments help repay a $215 million state loan. State incentives from the Mississippi Development Authority.

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Jan 26, 2024
    Amazon Web Services announced at least $10 billion for two data center campuses in Madison County, with about 1,000 jobs.
  • Feb 26, 2024
    Madison County Board of Supervisors approved the AWS site plan in a three-minute special meeting.
  • April 9, 2026
    Gov. Reeves announced Amazon would spend $11 billion more in Madison County, raising its Mississippi total to $25 billion.
  • Aug 17, 2026
    Madison County supervisors set a value of about $292 million on each of the five Canton buildings; Amazon had argued for about $70 million each.

Local votes and rules

๐Ÿ“Œ Other

Supervisors adopted the tax assessor's value of about $292 million for each of Amazon's five buildings at the Mega Site. Amazon had argued for about $70 million each and would not share its building costs. Amazon pays under a fee-in-lieu deal that also repays a $215 million state loan. Talks were to continue.

Aug 17, 2026
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Amazon-AWS Plans Madison County, Mississippi, Data Center Operations ยท Area Development ยท Jan 26, 2024
  2. Board of Supervisors approves site plan for Amazon Web Services ยท WLBT ยท Feb 26, 2024
  3. Amazon continues Mississippi expansion, announcing plans to invest a total of $25 billion across the Magnolia State ยท Office of Governor Tate Reeves ยท April 9, 2026
  4. Amazon is expanding data centers in central Mississippi, governor announces ยท Mississippi Free Press ยท April 9, 2026
  5. Madison County, Amazon spar over data center tax values ยท WLOX ยท Aug 18, 2026