Being builtBig (AI-size): 116 megawatts

AVAIO Digital "Taurus" data center campus in Brandon

Also called: AVAIO Digital Taurus, Taurus Data Center Hub

AVAIO Digital is building a $6 billion data center campus on about 175 acres in an industrial park in Brandon. The first phase, 116 megawatts, is due in 2027. Nearly 1,000 residents signed a petition asking for promises that power bills and pollution won't go up.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Brandon City.

Where things stand: Being built Announced Sept 2025; first phase (600,000+ sq ft, 116 MW) due in the first half of 2027.

❓ 4 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Sept 2025): Nearly 1,000 people signed a petition asking Rankin County supervisors for written promises of no higher bills and no pollution.

What we know

  • 📍 WhereEast Metropolitan Center Business and Industrial Park, Brandon, Rankin County
  • 🏢 CompanyAVAIO Digital Partners
  • 🌳 Size175 acres
  • ⚡ Power it needs116 megawatts (about as much as 92,800 homes)
  • 🔌 Where the power comes fromEntergy Mississippi; rooftop solar planned
  • ❄️ CoolingCompany promises water-efficient cooling and rainwater capture.
  • 💵 Cost$6 billion
  • 💸 Tax breaksState data center tax exemption approved by the Mississippi Development Authority; Rankin County and City of Brandon helped.
  • 👷 Jobs promised60

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water will the campus use? 🙋 I'll find out ·
  • Will Entergy Mississippi customers' bills rise because of this campus? 🙋 I'll find out ·
  • Which companies will rent space in it? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Sept 2025
      Gov. Reeves announced AVAIO Digital's $6 billion data center campus in Brandon, the third-largest investment in state history.
    • Sept 2025
      Nearly 1,000 people signed a petition asking Rankin County supervisors for written promises of no higher bills and no pollution.

    Local votes and rules

    🤝 Agreement with the company

    Rankin County and the City of Brandon made a deal with ADP Rankin Data Hub LLC to pay a set fee instead of regular property taxes (fee in lieu). It went to the state development agency (MDA) for final approval on Dec. 30, 2025. The terms were not in the agenda.

    Dec 30, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. AVAIO Digital plans $6 billion data center campus in Mississippi · Yahoo News · Sept 2025
    2. AVAIO Digital to construct $6 billion data center in Rankin County · SuperTalk Mississippi · Sept 2025
    3. Data center petition in Brandon · Mississippi Today · Sept 3, 2025