Rifle Range Road computing center (north of Marshfield)

Lumon Solutions is building a small 'AI-ready' computing center on 5 acres off Rifle Range Road north of Marshfield. The county says it will use a closed-loop cooling system and a private well, and the company asked for no tax breaks. Webster County has no zoning, so it had little say.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Webster County Commission (for land outside city and town limits).

Where things stand: Being built Site work started in spring 2026. The county said in June it cannot stop a project already under construction.

❓ 4 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (June 16, 2026): County adopted a six-month pause on new data centers, but said it would not use it to stop this project.

What we know

  • 📍 WhereRifle Range Road, just north of Marshfield city limits, next to a power substation, Unincorporated Webster County, Webster County
  • 🏢 CompanyLumon Solutions
  • 🌳 Size5 acres
  • 💧 Waterprivate well about 500 feet deep
  • ❄️ Coolingclosed-loop cooling
  • 💸 Tax breaksThe developer asked for no tax breaks, the county said.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much electricity will it use, and which power company serves it? 🙋 I'll find out ·
  • Will it have diesel backup generators? 🙋 I'll find out ·
  • Who will use the computing center? 🙋 I'll find out ·
  • Where exactly is the site on Rifle Range Road? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: the county only says the 5-acre site is on Rifle Range Road outside Marshfield. We could not find a parcel or address, so the pin stays on the town.

    What happened so far

    • April 22, 2026
      Residents raised concerns about a rumored data center on Rifle Range Road.
    • May 6, 2026
      County Commission said the developer described a small computing center on 5 acres with a 70-by-200-foot building.
    • May 11, 2026
      Hundreds packed a public meeting at Marshfield High School.
    • June 16, 2026
      County adopted a six-month pause on new data centers, but said it would not use it to stop this project.

    Local votes and rules

    ⏸️ Pause on new data centers

    County commission adopted a 6-month pause on new data centers, solar farms, wind farms and big battery sites in unincorporated areas. It said the pause will not be used to stop the data center already being built on Rifle Range Road.

    June 16, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Commission's statement on data centers · Webster County Commission · May 6, 2026
    2. County adopts six-month moratorium · Webster County Commission · June 16, 2026
    3. Hundreds pack Marshfield, Mo., meeting over planned AI data center · KY3 · May 11, 2026
    4. Rumors of data center in Webster County spark community concerns · KY3 · April 22, 2026