TierPoint data center (2300 Locust Street)
TierPoint is turning a 135,800-square-foot downtown building into a data center for business customers. It plans to invest up to $150 million.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of St. Louis City.
Where things stand: Being built TierPoint bought the building in 2024 and is converting it in phases.
❓ 2 open questions about it: see below.
Last checked Oct 10, 2026.
🕒 Latest update (Aug 2024): TierPoint announced it bought a 135,800-square-foot building to turn into a data center, investing up to $150 million.
What we know
- 📍 Where2300 Locust Street, downtown St. Louis, St. Louis, St. Louis city
- 🏢 CompanyTierPoint
- 👤 Built forTierPoint (colocation)
- ⚡ Power it needs20 megawatts (about as much as 16,000 homes)
- 💵 Cost$150 million
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is the TierPoint Locust Street data center open yet? 🙋 I'll find out ·
- How much power will it use? 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked the site location: a satellite image shows the downtown building at 2300 Locust Street at the pin.
What happened so far
- Aug 2024TierPoint announced it bought a 135,800-square-foot building to turn into a data center, investing up to $150 million.
Local votes and rules
📜 Data center rules
Board of Aldermen passed Board Bill 49 unanimously on Sept. 11, 2026, and Mayor Cara Spencer signed it on Sept. 17. It sorts data centers by size, keeps them out of homes areas, sets distance rules, bans water-heavy cooling and requires more renewable power over time.
🤝 Agreement with the company
City agency approved a community benefit plan for the Armory data center: $15.7 million paid to the city, no local tax breaks, job targets up to 100, renewable power goals, and damages if tax revenue falls short.
⚖️ Court case
A partner in TerraWatt, the developer, sued the Board of Adjustment to remove two permit conditions: a renewable energy requirement and a rule that the Board of Aldermen approve the community benefit agreement.
⚖️ Court case
Opponents asked a court to reverse the Board of Adjustment's decision that let the Armory data center go forward, and to pause it while the case goes on.
📌 Other
A plan to ban large data centers in St. Louis failed at the Board of Aldermen. Work on zoning rules went on instead.
✅ Approved
Board of Public Service unanimously approved a conditional use permit for the data center near the Armory. In July the Board of Adjustment let it go ahead with added rules, including 50% renewable power within 5 years, closed-loop cooling, and no diesel generator testing on bad air days.
📌 Other
Aldermen turned down a proposal to pause new data center applications while the city wrote its rules.
📌 Other
City leaders chose not to pause data centers. Instead Mayor Cara Spencer ordered staff to write data center rules within about five months, with public hearings required for every data center before a permit.
Drag the slider to compare the land before and now.
Where this comes from
- TierPoint Relocates-Expands St. Louis, Missouri, Operations · Area Development · Aug 15, 2024
- TierPoint to invest $150M in St. Louis, MO enterprise-grade data center · Business Facilities · 2024
- Census geocoder: 2300 Locust St, St. Louis, MO 63103 · U.S. Census Bureau · Oct 7, 2026
- USGS satellite image of the site · USGS The National Map · Oct 8, 2026
- TierPoint Acquires Downtown St. Louis Building for Newest Data Center · TierPoint · Aug 13, 2024
See something wrong? Tell us and we'll fix it.