Send us a tip
Approved, not built yetBig (AI-size): 120 megawatts

Armory Innovation District data center (Midtown St. Louis)

Also called: Armory data center

Developers plan a 120-megawatt data center in a former warehouse next to the Armory in Midtown St. Louis, part of a $3 billion project. The city approved it with conditions like using more renewable power. There is no tenant yet, and environmental groups appealed.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of St. Louis City.

Where things stand: Approved, not built yet Board of Public Service approved the permit April 21, 2026; Board of Adjustment rejected appeals July 30, 2026 with added rules.

❓ 4 open questions about it: see below.

Last checked Oct 20, 2026.

🕒 Latest update (Sept 15, 2026): The city's Land Clearance for Redevelopment Authority approved a community benefit plan: TerraWatt pays the city $15.7 million, cannot seek local tax breaks, must reach 100 jobs, and owes damages if tax revenue falls short.

What we know

  • 📍 Whereformer Famous-Barr/Macy's warehouse next to the historic Armory, Midtown, St. Louis, St. Louis city
  • 🏢 CompanyContour, TeraWatt, THO Investments and Steadfast City (development team)
  • 👤 Built forno tenant yet
  • ⚡ Power it needs120 megawatts (about as much as 96,000 homes)
  • 🔌 Where the power comes fromAmeren Missouri; permit requires 50% renewable energy within five years and on-site renewable power.
  • ❄️ Coolingclosed-loop cooling with air-cooled chillers
  • 💵 Cost$3 billion
  • 💸 Tax breaksDevelopers said they will not ask for tax breaks; city estimates $423 million in tax revenue over 10 years.
  • 👷 Jobs promised100

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who will be the tenant? 🙋 I'll find out ·
  • How many diesel backup generators will it have? 🙋 I'll find out ·
  • How much water will it use per day? 🙋 I'll find out ·
  • Will the courts uphold the permit and its conditions in the two lawsuits (one by opponents, one by the developer)? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: the data center is planned in the old Famous-Barr warehouse on Market Street, just west of the Armory. A satellite image shows the large warehouse there. The pin is on it.

    What happened so far

    • April 21, 2026
      Board of Public Service unanimously approved a conditional use permit.
    • July 30, 2026
      Board of Adjustment voted unanimously to let it go forward with new rules, including no diesel generator testing on bad air days.
    • Aug 28, 2026
      Opponents sued in city court to overturn the Board of Adjustment's decision to grant the permit.
    • Sept 2026
      A TerraWatt partner sued the city's Board of Adjustment to remove two permit conditions: the renewable energy requirement and Board of Aldermen approval of the community benefit agreement.
    • Sept 15, 2026
      The city's Land Clearance for Redevelopment Authority approved a community benefit plan: TerraWatt pays the city $15.7 million, cannot seek local tax breaks, must reach 100 jobs, and owes damages if tax revenue falls short.

    Local votes and rules

    📜 Data center rules

    Board of Aldermen passed Board Bill 49 unanimously on Sept. 11, 2026, and Mayor Cara Spencer signed it on Sept. 17. It sorts data centers by size, keeps them out of homes areas, sets distance rules, bans water-heavy cooling and requires more renewable power over time.

    Sept 17, 2026

    🤝 Agreement with the company

    City agency approved a community benefit plan for the Armory data center: $15.7 million paid to the city, no local tax breaks, job targets up to 100, renewable power goals, and damages if tax revenue falls short.

    Sept 15, 2026

    ⚖️ Court case

    A partner in TerraWatt, the developer, sued the Board of Adjustment to remove two permit conditions: a renewable energy requirement and a rule that the Board of Aldermen approve the community benefit agreement.

    Sept 2026

    ⚖️ Court case

    Opponents asked a court to reverse the Board of Adjustment's decision that let the Armory data center go forward, and to pause it while the case goes on.

    Aug 28, 2026

    📌 Other

    A plan to ban large data centers in St. Louis failed at the Board of Aldermen. Work on zoning rules went on instead.

    June 2026

    ✅ Approved

    Board of Public Service unanimously approved a conditional use permit for the data center near the Armory. In July the Board of Adjustment let it go ahead with added rules, including 50% renewable power within 5 years, closed-loop cooling, and no diesel generator testing on bad air days.

    April 21, 2026

    📌 Other

    Aldermen turned down a proposal to pause new data center applications while the city wrote its rules.

    Feb 2026

    📌 Other

    City leaders chose not to pause data centers. Instead Mayor Cara Spencer ordered staff to write data center rules within about five months, with public hearings required for every data center before a permit.

    Sept 18, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Data center project near Armory gets final approval from city · St. Louis American · April 21, 2026
    2. St. Louis board allows data center near Armory to move forward with new rules · St. Louis Public Radio · July 30, 2026
    3. Explained: St. Louis-area data center regulations · St. Louis Public Radio · Aug 21, 2026
    4. New plan: Armory to be $3B tech hub with nearby data center (warehouse west of the Armory) · St. Louis Public Radio · Jan 16, 2026
    5. Armory, 3660 Market St geocoded · US Census Geocoder · Oct 8, 2026
    6. USGS satellite image of the site · USGS The National Map · Oct 8, 2026
    7. Opponents of St. Louis data center take fight to court · St. Louis Public Radio · Aug 29, 2026
    8. St. Louis okays Midtown data center plan with tax revenue promises · St. Louis Public Radio · Sept 15, 2026
    9. Developer of St. Louis data center at Armory files lawsuit against city · St. Louis Public Radio · Sept 17, 2026

    See something wrong? Tell us and we'll fix it.