Capstone Technology Campus (Pickett Road, St. Joseph)

A local developer asked St. Joseph to annex and rezone 130 acres on Pickett Road for four data center buildings and a substation. Residents signed petitions against it. The applications were withdrawn in June 2026.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Rezoning and annexation applications were withdrawn June 26, 2026.

๐Ÿ•’ Latest update (June 26, 2026): City confirmed both rezoning and annexation applications were withdrawn at the developer's request.

What we know

  • ๐Ÿ“ Where6321 and 5701 Pickett Road (land outside city limits; annexation was requested), St. Joseph, Buchanan County
  • ๐Ÿข CompanyCapstone Technology Campus
  • ๐Ÿ‘ค Built forAtmosphere Data Centers (planned operator)
  • ๐ŸŒณ Size130 acres

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • June 26, 2026
    City confirmed both rezoning and annexation applications were withdrawn at the developer's request.
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Developer withdraws data center proposal in St. Joseph, Missouri ยท Baxtel ยท June 30, 2026
  2. Local businessman withdraws application for data center in St. Joseph, Missouri ยท Data Center Dynamics ยท June 2026

See something wrong? Tell us and we'll fix it.