Stopped or cancelledBig (AI-size): 440 acres

Project Cumulus (off Highway 370, St. Charles)

Also called: Project Cumulus, CRG Cumulus

CRG proposed a $1 billion data center called Project Cumulus on about 440 acres off Highway 370 in St. Charles, near the city's drinking water wells. Residents objected to the secrecy and water and power use. The developer withdrew in 2025, and the city later banned large data centers.

✔ ConfirmedSourceLast checked: Oct 7, 2026

What happens next?

Where things stand: Stopped or cancelled Developer withdrew in August 2025; the city then paused and in May 2026 banned large data centers.

❓ 1 open question about it: see below.

📣 See work going on anyway? Tell us

Last checked Oct 7, 2026.

🕒 Latest update (May 2026): City Council voted to ban large data centers in city limits.

What we know

  • 📍 Whereoff Highway 370, near the city's well field, St. Charles, St. Charles County
  • 🏢 CompanyCRG Cumulus LLC
  • 🏛️ Owned byCRG
  • 👤 Built forunknown (news reports tied it to Google)
  • 🌳 Size440 acres
  • 💵 Cost$1 billion
  • 🤐 Privacy agreement (NDA)Yes. After the fight, the mayor said the city will no longer sign agreements with data center developers to keep plans private (NDAs).

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Was Google the planned user of Project Cumulus? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Aug 2025
      Developer withdrew its application before an Aug. 19 council vote.
    • Aug 22, 2025
      City Council passed a one-year pause on new data center applications.
    • May 2026
      City Council voted to ban large data centers in city limits.

    Local votes and rules

    🚫 Ban

    City council voted 7-1 for Bill 14085. Data centers are no longer allowed in any zoning district in the city, so large data centers are banned. It makes the 2025 pause permanent.

    May 19, 2026

    ⏸️ Pause on new data centers

    City council voted unanimously in a special meeting to stop taking applications for new or bigger data centers for one year. It came after anger over a secret AI data center plan near the city's wells. In May 2026 a permanent ban replaced it.

    Aug 22, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. St. Charles data center moratorium · Spectrum News · Aug 22, 2025
    2. St. Charles places a 1-year pause on data center projects · First Alert 4 (KMOV) · Aug 23, 2025
    3. St. Charles passes a ban on data centers · St. Louis Public Radio · May 20, 2026