📣 Report Something
Stopped or cancelled

20-story data center tower (Western Newspaper Union building, Quality Hill)

A Miami developer wanted to build a 20-story data center tower on top of a historic building in Quality Hill. The City Plan Commission voted 6-0 against it in August 2026. The mayor said the City Council is unlikely to approve it.

✔ ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: City Plan Commission voted 6-0 to deny it on Aug. 5, 2026. The developer could still ask the City Council.

🕒 Latest update (Aug 5, 2026): City Plan Commission voted 6-0 to deny the 384-foot data center tower; 475 letters opposed it.

What we know

  • 📍 Where934 Central Street (10th and Central), Quality Hill, downtown Kansas City, Kansas City, Jackson County
  • 🏢 CompanyRevitalization Unlimited
  • 🔌 Where the power comes fromDeveloper said it expected to use Bloom Energy fuel cells.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • June 2026
    Developer met with the city's Development Review Committee.
  • Aug 5, 2026
    City Plan Commission voted 6-0 to deny the 384-foot data center tower; 475 letters opposed it.

Local votes and rules

✋ Turned down

City Plan Commission voted 6-0 to deny a 20-story, 384-foot data center tower at 10th and Central in Quality Hill, in a historic building. 475 letters opposed it. The developer could still ask the City Council to overrule.

Aug 5, 2026

📜 Data center rules

City council voted unanimously for new zoning rules. Data centers are now treated as industrial, can only go in certain zones, and big ones need a council vote plus letters from KC Water and Evergy saying they can serve them.

Jan 15, 2026
🛰️ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

📣 Report something