Send us a tip
Built & runningBig (AI-size): 375 acres

Meta Kansas City data center (Golden Plains Technology Park)

Meta runs a large data center of nearly 1 million square feet in the Golden Plains Technology Park in the Kansas City Northland. It cost about $1 billion and came online in 2025 after delays.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

Where things stand: Built & running Meta brought the data center online in 2025.

❓ 2 open questions about it: see below.

📣 Report noise, water or power bill changes

Last checked Oct 10, 2026.

🕒 Latest update (2025): Meta brought the $1 billion data center online.

What we know

  • 📍 WhereGolden Plains Technology Park, 801 NW 128th Street, Kansas City Northland (park spans Platte and Clay counties), Kansas City, Platte County
  • 🏢 CompanyDiode Ventures (tech park)
  • 👤 Built forMeta
  • 🌳 Size375 acres
  • 🔌 Where the power comes fromMeta says its electricity is matched with 100% clean and renewable energy.
  • 💵 Cost$1 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water does the Meta data center use per day? 🙋 I'll find out ·
  • How much power does it use? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: OpenStreetMap maps the Meta Kansas City Data Center along NW 128th Street, and a 2024 satellite image shows the large buildings there. The pin is the centre of the campus.

    What happened so far

    • 2022
      Meta picked Kansas City for a data center in the Golden Plains Technology Park; construction began.
    • 2025
      Meta brought the $1 billion data center online.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Meta Brings $1B Data Center Online · Commercial Search · 2025
    2. Facebook coming to Kansas City: Meta selects KCMO for massive $800M data center · Flatland KC · 2022
    3. Data center developers look to rural Missouri for acreage, power · News Tribune · March 27, 2026
    4. Meta Kansas City Data Center (operator Meta), with building outline way 1184066765 · OpenStreetMap · Oct 8, 2026
    5. 801 NW 128th St, Kansas City, MO position · OpenStreetMap Nominatim · Oct 8, 2026
    6. Sentinel-2 cloudless 2024 satellite image of the site · EOX / Copernicus Sentinel-2 · Oct 8, 2026
    7. Facebook parent company to bring $800 million data center to Kansas City · KCTV5 · March 24, 2022
    8. Facebook headed to Northland · Platte County Landmark · March 16, 2022

    See something wrong? Tell us and we'll fix it.