Send us a tip
Being builtBig (AI-size): 700 megawatts

Google Project Mica campus (Kansas City Northland)

Also called: Project Mica

Google is building a second, larger campus in the Kansas City Northland called Project Mica. Plans call for five big buildings on about 500 acres, about $10 billion of investment, and about 700 megawatts of power. Google says it will pay the full cost of the power it uses.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Kansas City City.

Where things stand: Being built Google confirmed the campus in February 2026; construction has started.

❓ 3 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Feb 12, 2026): Google confirmed a $10 billion, five-building campus on about 500 acres.

What we know

  • 📍 Where12701 N Arrowhead Trafficway, northeast of I-435 and U.S. 169, Kansas City, Clay County
  • 🏢 CompanyGoogle
  • 🏛️ Owned byAlphabet
  • 👤 Built forGoogle
  • 🌳 Size500 acres
  • ⚡ Power it needs700 megawatts (about as much as 560,000 homes)
  • 🔌 Where the power comes fromEvergy; Google agreed to cover the full energy costs of powering the campus.
  • 💵 Cost$10 billion
  • 💸 Tax breaksPort KC approved up to $10 billion in revenue bonds for the project. Google agreed to give $1.5 million to the Smithville School District workforce program and $250,000 to the Northland career center.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water will Project Mica use per day? 🙋 I'll find out ·
  • Will new power lines or substations be built for it? 🙋 I'll find out ·
  • How many permanent jobs will it have? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: OpenStreetMap maps a construction area named Google Project Mica Data Center northeast of I-435 and U.S. 169, matching news reports. Satellite images from 2024 still show fields there; construction started in 2026.

    What happened so far

    • 2023
      Diode Ventures first brought the Project Mica site forward; Google later took it over.
    • Feb 12, 2026
      Google confirmed a $10 billion, five-building campus on about 500 acres.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Google confirms new data center development in Kansas City's Northland · KCTV5 · Feb 12, 2026
    2. Google confirms $10B Project Mica in KC · Axios Kansas City · Feb 12, 2026
    3. Google confirms $10B, 500-acre data center in Kansas City's Northland · Yahoo News · Feb 2026
    4. Google begins construction on second data center campus in Kansas City, Missouri · Baxtel · Feb 2026
    5. Google Project Mica Data Center (construction area) · OpenStreetMap · Oct 8, 2026
    6. Sentinel-2 cloudless 2024 satellite image of the site · EOX / Copernicus Sentinel-2 · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.