Approved, not built yetBig (AI-size): 600 acres

Wildwood Ranch data center site (west Joplin)

Also called: Wildwood Ranch Industrial Complex

The owner of Wildwood Ranch asked Joplin to annex and rezone about 600 acres in west Joplin for a data center. The council approved both in early 2026 after packed meetings. No tech company or builder has been named, and no building permit has been filed.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Joplin City.

Where things stand: Approved, not built yet Council annexed and rezoned the land for heavy industry in Feb. 2026. No builder or building permit yet; a power study was underway.

❓ 4 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Oct 8, 2026): We placed the pin at the southwest corner of Central City Road and West 20th Street, where the city's Wildwood Ranch page puts the site.

What we know

  • 📍 WhereSouthwest corner of Central City Road and West 20th Street, west Joplin, Joplin, Jasper County
  • 🏢 CompanyWildwood Ranch LLC
  • 🌳 Size600 acres
  • 🔌 Where the power comes fromLiberty (Empire District Electric) said it has enough capacity; developer would pay for hookups.
  • 💧 WaterMissouri American Water (said it has enough capacity)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which company will build and run the data center? 🙋 I'll find out ·
  • How much power will it use? Reports range from 100 to 200 megawatts. 🙋 I'll find out ·
  • How much water will it use per day? 🙋 I'll find out ·
  • Will the city give tax breaks? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Dec 4, 2025
      Landowner company asked the city to annex and rezone about 600 acres from homes to heavy industry.
    • Jan 20, 2026
      After seven hours of public comment, council gave first approval: annexation 6-3, rezoning 7-2.
    • Feb 17, 2026
      Council gave final approval to the annexation and rezoning.
    • March 10, 2026
      Resident petitions to force a public vote fell short: 2,832 signatures, with 5,032 needed.
    • Oct 8, 2026
      We placed the pin at the southwest corner of Central City Road and West 20th Street, where the city's Wildwood Ranch page puts the site.

    Local votes and rules

    🗺️ Zoning change

    After a 7-hour hearing in January (annexation 6-3, rezoning 7-2), the council gave final approval to annex and rezone about 600 acres at Wildwood Ranch from homes to heavy industry for a possible data center. Resident petitions to force a public vote fell short in March.

    Feb 17, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Joplin approves annexation and rezoning for potential data center · KSMU · Jan 21, 2026
    2. Joplin group plans to fight data center using referendum, petition process · Joplin Globe (via Yahoo News) · Jan 2026
    3. Wildwood Ranch Industrial Complex · City of Joplin · March 6, 2026
    4. Petitions to stop Joplin data center project fall short of goal · Joplin Globe · March 10, 2026
    5. Central City Road, Jasper County, Missouri position · OpenStreetMap Nominatim · Oct 8, 2026
    6. West 20th Street, Joplin, Missouri position · OpenStreetMap Nominatim · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.