Crusoe data center near Kingdom City (Callaway County)
Crusoe wants to build two large data center buildings on about 200 acres of farmland near Kingdom City. It would cost about $4.5 billion. Callaway County has no zoning, so the county's main say is over tax breaks.
Where things stand: Crusoe presented plans in July 2026. No land purchase or water deal yet; county is discussing an 80% personal property tax break.
๐ Latest update (July 24, 2026): County commissioners said the deal is not final; no land purchase or water district agreement yet.
What we know
- ๐ Wherealong County Road 240, near Kingdom City (exact site not made public), Unincorporated Callaway County, Callaway County
- ๐ข CompanyCrusoe
- ๐ณ Size200 acres
- โ๏ธ Cooling100% air cooling (per company)
- ๐ต Cost$4.5 billion
- ๐ธ Tax breaksCounty commissioners said they would settle on an 80% personal property tax break and no real estate tax break; not final as of July 2026.
- ๐ท Jobs promised70
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Where exactly is the site? ๐ I'll find out
- How much power will it need, and will new power lines be built? ๐ I'll find out
- Did the county approve the tax break? ๐ I'll find out
What happened so far
- July 14, 2026Crusoe unveiled plans for a $4.5 billion data center in Callaway County at an open house.
- July 24, 2026County commissioners said the deal is not final; no land purchase or water district agreement yet.
๐ฐ๏ธ See it from above
An aerial photo of the area.
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Data center developer, Callaway officials address concerns ยท News Tribune ยท July 15, 2026
- AI infrastructure company unveils plans for Callaway County data center ยท ABC 17 News ยท July 14, 2026