Stopped or cancelledBig (AI-size): 679 acres

North Mankato Northport data center idea (Oppidan)

An environmental study looked at a possible data center campus of up to 4 million square feet on about 679 acres near North Mankato. Developer Oppidan pulled out in 2025 before applying. The city had signed an agreement with Oppidan to keep the plans private (NDA) in 2023.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

Where things stand: Stopped or cancelled Oppidan dropped out in 2025 before filing any application.

❓ 1 open question about it: see below.

📣 See work going on anyway? Tell us

Last checked Oct 10, 2026.

🕒 Latest update (Aug 5, 2025): MCEA sued the city over the environmental review.

What we know

  • 📍 WhereNorthport Industrial Park area off Lookout Drive (about 679 acres, outside city limits), North Mankato, Nicollet County
  • 🏢 CompanyOppidan
  • 🌳 Size679 acres
  • 🤐 Privacy agreement (NDA)Yes. The city signed an agreement with Oppidan to keep the plans private (NDA) in July 2023, according to records.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • July 2023
      City signed a confidentiality agreement (NDA) with Oppidan.
    • 2025
      Oppidan ended its involvement; the city said no application was ever filed. MCEA later dropped its lawsuit.
    • Aug 5, 2025
      MCEA sued the city over the environmental review.

    Local votes and rules

    ⏸️ Pause on new data centers

    North Mankato held a packed hearing on a pause for large data centers and put off the vote to fix the wording. The newer draft covers data centers over 150,000 square feet or using over 50,000 gallons of water a day.

    Aug 3, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Data center plans stalled in North Mankato after developer backs out · Mankato Free Press · Nov 17, 2025
    2. Legal updates on MCEA's data center cases · Minnesota Center for Environmental Advocacy · May 15, 2026

    See something wrong? Tell us and we'll fix it.