CloudHQ plans a 1.4 million square foot data center campus on 70 acres in southwest Chaska, costing about $1 billion. It has early city approvals. A new electric substation would still need its own approval.

๐Ÿ‘ฅ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: Has early city approvals. Final approval for the data center and a new substation were still to come as of 2025.

๐Ÿ•’ Latest update (April 15, 2025): Report: CloudHQ has site control, early city approvals, and clearance to build a berm on part of the site.

What we know

  • ๐Ÿ“ WhereNorth of Engler Boulevard and west of Clover Ridge Drive, Chaska, Carver County
  • ๐Ÿข CompanyCloudHQ
  • ๐ŸŒณ Size70 acres
  • ๐Ÿ’ต Cost$1 billion

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • April 15, 2025
    Report: CloudHQ has site control, early city approvals, and clearance to build a berm on part of the site.
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Data center drives development for Minnesota city ยท BridgeTower Media / The Daily Reporter ยท April 15, 2025

See something wrong? Tell us and we'll fix it.