Approved, not built yet
CloudHQ MSP data center campus (Chaska)
Also called: CloudHQ MSP Campus
CloudHQ plans a 1.4 million square foot data center campus on 70 acres in southwest Chaska, costing about $1 billion. It has early city approvals. A new electric substation would still need its own approval.
Where things stand: Has early city approvals. Final approval for the data center and a new substation were still to come as of 2025.
๐ Latest update (April 15, 2025): Report: CloudHQ has site control, early city approvals, and clearance to build a berm on part of the site.
What we know
- ๐ WhereNorth of Engler Boulevard and west of Clover Ridge Drive, Chaska, Carver County
- ๐ข CompanyCloudHQ
- ๐ณ Size70 acres
- ๐ต Cost$1 billion
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has CloudHQ received final city approval and started building? ๐ I'll find out
- How much power and water will the campus use? ๐ I'll find out
What happened so far
- April 15, 2025Report: CloudHQ has site control, early city approvals, and clearance to build a berm on part of the site.
๐ฐ๏ธ See it from above
An aerial photo of the area.
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Data center drives development for Minnesota city ยท BridgeTower Media / The Daily Reporter ยท April 15, 2025
See something wrong? Tell us and we'll fix it.