Proposed

Wixom Industrial One data center, South Wixom Road

A developer wants a three-building, 519,000 square foot data center campus on 54 acres on South Wixom Road. The city paused data centers and refused a waiver. The developer sued, saying the land was already zoned for it.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Wixom City.

Where things stand: Proposed Blocked by a city pause since March 2026; the landowner sued the city in federal court on Aug. 7, 2026.

❓ 2 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Aug 7, 2026): Wixom Industrial One sued the city in U.S. District Court in Detroit.

What we know

  • 📍 Where30625 S. Wixom Road, Wixom, Wixom, Oakland County
  • 🏢 CompanyWixom Industrial One and Sansone Group
  • 🌳 Size54 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who would use the data center, and how much power would it need? 🙋 I'll find out ·
  • Has the court ruled on the lawsuit? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: news reports give the address 30625 S. Wixom Road, which we placed with the Census geocoder.

    What happened so far

    • March 2026
      City adopted a six-month pause (moratorium) on data centers.
    • July 2026
      City council rejected the developer's request for a waiver from the pause.
    • Aug 7, 2026
      Wixom Industrial One sued the city in U.S. District Court in Detroit.

    Local votes and rules

    ⚖️ Court case

    Developer Wixom Industrial One sued Wixom in federal court. It says the city broke state zoning law by pausing data centers and writing rules that would block its 54-acre project north of I-96, on land already zoned for it.

    Aug 7, 2026

    📜 Data center rules

    Wixom reportedly ended its pause early and adopted strict data center rules: a 1,500-foot buffer from homes, schools and parks, no use of well water, and required sound studies.

    Aug 2026

    ⏸️ Pause on new data centers

    Wixom paused data centers for six months after a developer showed plans for a three-building campus. The council refused the developer's request to lift it early.

    March 24, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Developer sues City of Wixom over data center moratorium · WHMI · Aug 12, 2026
    2. How many AI data centers are planned in Michigan? We counted. · Gander Newsroom · March 2, 2026
    3. Michigan city rejects data center waiver request · GovTech · Oct 8, 2026
    4. Census geocoder: 30625 S Wixom Rd, Wixom · US Census Bureau · Oct 8, 2026