Proposed data center campus near US-131 and 17 Mile Road, Solon Township

Also called: Project Peninsula

An unnamed tech company is looking at farmland near US-131 in Solon Township for a large data center. No plans have been filed. The township paused data centers while it writes rules, and residents strongly oppose it.

👥 Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: No application filed. Township pause on data centers extended to Feb. 9, 2027.

🕒 Latest update (July 13, 2026): Township extended the pause until Feb. 9, 2027.

What we know

  • 📍 WhereWest of US-131 between 16 and 17 Mile roads, behind the Cedarfield neighborhood, Solon, Kent County
  • 🏢 Companyunknown

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which company is behind the plan? A local tracker names Venerly LLC ('Project Peninsula'); this is not confirmed by the township. 🙋 I'll find out
  • How many acres would it use? 🙋 I'll find out

What happened so far

  • Feb 2026
    Township adopted a six-month pause on data centers.
  • July 13, 2026
    Township extended the pause until Feb. 9, 2027.

Local votes and rules

⏸️ Pause on new data centers

Solon Township paused zoning and building applications for data centers and crypto mining for six months (its planning commission had suggested 90 days). On July 13, 2026 the board extended it to Feb. 9, 2027, citing heavy public comment and pending state bills.

Feb 9, 2026
🛰️ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

📣 Report something