ProposedBig (AI-size): 270 acres

Marshall Technology & Energy Center, Brooks Industrial Park

Also called: Marshall Technology & Energy Center

Alterra Development wants to build a data center on about 270 acres in Marshall's Brooks Industrial Park, near a wetland and lake. It was first planned at 1 gigawatt with a gas plant; the company later dropped the gas plant. The city paused approvals for a year to write noise rules.

✔ ConfirmedSourceLast checked: Oct 7, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Marshall City.

Where things stand: Proposed City approved a one-year pause on data center approvals on Aug. 3, 2026.

❓ 2 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (Aug 3, 2026): City council approved a 365-day pause (moratorium) on data center approvals.

What we know

  • 📍 WhereBrooks Industrial Park, next to the Brooks wetland and nature area, Marshall, Calhoun County
  • 🏢 CompanyAlterra Development
  • 🌳 Size270 acres
  • 🔌 Where the power comes fromA gas power plant on site was first planned, then dropped by the company.
  • ❄️ Coolingclosed-loop liquid cooling (company claim)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many megawatts is the smaller plan, and where will the power come from? 🙋 I'll find out ·
  • How much water would it use? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Oct 2025
      City authorized a purchase agreement with Alterra for about 270 acres.
    • Aug 3, 2026
      City council approved a 365-day pause (moratorium) on data center approvals.

    Local votes and rules

    ⏸️ Pause on new data centers

    Marshall City Council paused approval of any data center in the city for 365 days, citing power, water and heat concerns, and plans a rule on low-frequency noise. Alterra, which plans a project on 270 acres at Brooks Industrial Park, has dropped its planned gas power plant.

    Aug 10, 2026

    ⏸️ Pause on new data centers

    Marengo Township voted 5-0 to stop data center permits, approvals and building for one year while it writes rules.

    Feb 24, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Marshall data center moratorium delays development by at least one year · WWMT · Aug 10, 2026
    2. How many AI data centers are planned in Michigan? We counted. · Gander Newsroom · March 2, 2026