Lenox Township 1,400-acre rezoning request (possible data center campus)
Also called: Lenox & Chesterfield Development Alliance
A company called Lenox & Chesterfield Development Alliance asked Lenox Township to rezone 1,400 acres. The request does not say what would be built, but the company's lawyers earlier wrote to the township supervisor about a data center campus. In September 2026 the supervisor said he does not want a data center in the township.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Township Board of Lenox Township.
Where things stand: Proposed Planning commission public hearing on the 1,402-acre rezoning (to Light Industrial) set for Nov. 16, 2026. The request names no use, but the company's lawyers earlier wrote of a data center campus.
❓ 2 open questions about it: see below.
Last checked Nov 16, 2026.
🕒 Latest update (Nov 2026): A conceptual plan filed with the rezoning request shows 10 buildings totaling about 2 million square feet and an on-site electrical substation or switchyard.
What we know
- 📍 Where48 parcels east of Gratiot Ave. and west of Frost Rd., between 29 Mile Rd. and 26 Mile Rd., Lenox, Macomb County
- 🏢 CompanyLenox & Chesterfield Development Alliance, LLC
- 🌳 Size1,402 acres
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is a data center company or end user behind the request? 🙋 I'll find out ·
- What did the planning commission recommend after the Nov. 16, 2026 hearing, and when will the township board vote on the rezoning? 🙋 I'll find out ·
What happened so far
- Jan 2026A data center developer asked to meet with the township; the township says it gave no letter of support.
- Oct 31, 2026The township published notice of a Nov. 16 public hearing on rezoning about 1,402 acres from Single Family Residential, Agriculture and General Business to Light Industrial.
- Nov 2026Lenox & Chesterfield Development Alliance, LLC asked Lenox Township to rezone 1,400 acres. Its lawyers had earlier written to the supervisor about a data center campus.
- Nov 2026A conceptual plan filed with the rezoning request shows 10 buildings totaling about 2 million square feet and an on-site electrical substation or switchyard.
Local votes and rules
⏸️ Pause on new data centers
Lenox Township paused data centers for four months, with an option to extend, while it studied rules. In summer 2026 its planning commission worked on a 'High Resource Demand Facilities' ordinance.
Drag the slider to compare the land before and now.
Where this comes from
- Michigan Data Centers: The Weekly Download · Michigan Advance · Nov 9, 2026
- Data center concerns have Lenox Township residents demanding transparency · WDIV ClickOnDetroit · Sept 3, 2026
- Public hearing notice: rezoning request, Lenox & Chesterfield Economic Development Alliance LLC · Charter Township of Lenox · Oct 31, 2026
- Planning Commission special meeting agenda, Nov. 16, 2026 · Charter Township of Lenox · Nov 1, 2026
- Lenox Township to weigh rezoning of 1,402 acres for light industrial project amid data center fears · WXYZ Detroit · Nov 2026
- Michigan Data Centers: The Weekly Download · Michigan Advance · Nov 16, 2026
See something wrong? Tell us and we'll fix it.