Stopped or cancelled

Proposed $1 billion data center, Howell Township

Randee LLC, working for an unnamed Fortune 100 company, asked to rezone about 1,000 acres of farmland for a $1 billion data center. After strong opposition and a six-month township pause, it withdrew. Township officials expect it may reapply.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Developer withdrew its rezoning request on Dec. 7, 2025, but may come back after the township writes rules.

πŸ•’ Latest update (Dec 7, 2025): Developer withdrew its rezoning request.

What we know

  • πŸ“ WhereFarmland north of I-96, Howell, Livingston County
  • 🏒 CompanyRandee LLC
  • 🌳 Size1,077 acres
  • πŸ’΅ Cost$1 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Dec 7, 2025
    Developer withdrew its rezoning request.

Local votes and rules

⏸️ Pause on new data centers

Howell Township trustees unanimously banned new data centers for six months. A developer had asked to rezone about 1,000 acres of farmland for a $1 billion data center, and later withdrew.

Nov 20, 2025
πŸ›°οΈ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Developer withdraws rezoning application for proposed data center in Howell Township Β· CBS Detroit Β· Dec 8, 2025
  2. Howell Township data center win Β· FracTracker Alliance Β· Jan 2026

See something wrong? Tell us and we'll fix it.