Stopped or cancelledBig (AI-size): 1,077 acres

Proposed $1 billion data center, Howell Township

Randee LLC, working for an unnamed Fortune 100 company, asked to rezone about 1,000 acres of farmland for a $1 billion data center. After strong opposition and a six-month township pause, it withdrew. Township officials expect it may reapply.

✔ ConfirmedSourceLast checked: Oct 7, 2026

What happens next?

Where things stand: Stopped or cancelled Developer withdrew its rezoning request on Dec. 7, 2025, but may come back after the township writes rules.

❓ 2 open questions about it: see below.

📣 See work going on anyway? Tell us

Last checked Oct 7, 2026.

🕒 Latest update (Dec 7, 2025): Developer withdrew its rezoning request.

What we know

  • 📍 WhereFarmland north of I-96, Howell, Livingston County
  • 🏢 CompanyRandee LLC
  • 🌳 Size1,077 acres
  • 💵 Cost$1 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which company was behind the project? A township trustee said Meta, but this is not confirmed. 🙋 I'll find out ·
  • Will the developer reapply after the township adopts rules? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Dec 7, 2025
      Developer withdrew its rezoning request.

    Local votes and rules

    📜 Data center rules

    Township officials told their attorney to draft an ordinance that would ban officials, staff and contractors from signing agreements to keep plans private (NDAs). It follows the data center proposal that is now on hold.

    Nov 2026

    ⏸️ Pause on new data centers

    The township board voted unanimously to extend its data center pause by six more months. The pause had been set to end on Nov. 20, 2026.

    Oct 2026

    ⏸️ Pause on new data centers

    Howell Township trustees unanimously banned new data centers for six months. A developer had asked to rezone about 1,000 acres of farmland for a $1 billion data center, and later withdrew.

    Nov 20, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Developer withdraws rezoning application for proposed data center in Howell Township · CBS Detroit · Dec 8, 2025
    2. Howell Township data center win · FracTracker Alliance · Jan 2026

    See something wrong? Tell us and we'll fix it.