ProposedBig (AI-size): 270 acres

Microsoft data center, Dorr Township

Microsoft bought nearly 270 acres next to US-131 in Dorr Township and says it plans a data center there. It had not filed a development plan by late 2025. Residents have raised concerns about water and power use.

👥 Reported, not confirmed yetSourceLast checked: Oct 7, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Board of Dorr Township.

Where things stand: Proposed Microsoft owns the land; the township was still waiting for a development plan in Dec. 2025.

❓ 2 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (Dec 2025): Microsoft told the township it plans a data center and hoped to start work in spring 2026.

What we know

  • 📍 WhereNext to US-131 (144th Avenue area), Dorr, Allegan County
  • 🏢 CompanyMicrosoft
  • 👤 Built forMicrosoft
  • 🌳 Size270 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Has Microsoft filed a site plan with Dorr Township? 🙋 I'll find out ·
  • How much power and water would the data center use? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • 2024
      Microsoft bought more than 200 acres near US-131 in Dorr Township.
    • Dec 2025
      Microsoft told the township it plans a data center and hoped to start work in spring 2026.

    Local votes and rules

    ⏸️ Pause on new data centers

    Dorr Township's board chose a 12-month pause on data centers, instead of the six months its lawyer suggested, so the planning commission has time to write rules. Microsoft owns about 272 acres there.

    Feb 26, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Microsoft plans a data center in Allegan County · WMUK · Dec 22, 2025
    2. How many AI data centers are planned in Michigan? We counted. · Gander Newsroom · March 2, 2026

    See something wrong? Tell us and we'll fix it.