Stopped or cancelled

Data center in Scarborough Technology Park

Also called: Scarborough High Technology Industrial Park

A landowner proposed a two-story data center on 52 acres in Scarborough, powered by gas fuel cells. Town planners said the application was incomplete. The town then paused data centers for 180 days.

βœ” ConfirmedSourceLast checked: Oct 2026

Where things stand: Town planners rejected the plan as incomplete in April 2026. Town then paused new data centers for 180 days.

πŸ•’ Latest update (June 2026): Town Council passed a 180-day data center moratorium, back-dated to April 1.

What we know

  • πŸ“ WhereAbout 52 acres just west of the Maine Turnpike, Scarborough, Cumberland County
  • 🏒 Companynot named (local landowner)
  • 🌳 Size52 acres
  • πŸ”Œ Where the power comes fromFuel cells running on natural gas, on site
  • ❄️ CoolingClosed-loop water cooling

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

πŸ”Ž What we checked

  • Oct 8, 2026: We checked news reports: they only say the 52 acres are on the west side of Scarborough, just west of the Maine Turnpike. No road, address or parcel number is public, so the pin stays on the town.

What happened so far

  • April 2026
    Master plan with a two-story data center filed with the town.
  • April 2026
    Planning office rejected the application as incomplete.
  • June 2026
    Town Council passed a 180-day data center moratorium, back-dated to April 1.

Local votes and rules

🚫 Ban

Scarborough Town Council is weighing a zoning change to ban data centers in every zone. The council voted unanimously to send it to the planning board. A second hearing is set for Oct. 21, 2026.

Sept 17, 2026

⏸️ Pause on new data centers

Scarborough Town Council unanimously passed a 180-day data center pause. It reaches back to applications filed on or after April 1, 2026, which covers the Scarborough Technology Park plan.

June 3, 2026
πŸ›°οΈ See it from above

Drag the slider to compare the land before and now.

20182025
We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Scarborough considers data center pause after development proposal Β· Maine Public Β· May 6, 2026
  2. Brunswick, Scarborough enact data center moratoriums Β· Spectrum News Maine Β· June 8, 2026
  3. Scarborough Town Council imposes data center moratorium Β· Portland Press Herald Β· June 3, 2026

See something wrong? Tell us and we'll fix it.