Appeal Digital Park (Natelli Holdings)

Also called: Natelli data center Lusby

Natelli Holdings wants to buy 133 acres of county land in Lusby for a data center campus costing over $3 billion. It would use treated wastewater for cooling and offered to build a $30 million park.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Developer asked to buy 133 acres of county land in March 2026. No sale or approval reported; county paused new data center applications in Aug. 2026.

πŸ•’ Latest update (Aug 18, 2026): County commissioners passed a six-month pause on new data center applications.

What we know

  • πŸ“ WhereCounty land on Route 2/4 in Lusby near Calvert Cliffs State Park, a former Dominion Cove Point construction yard next to a landfill, Unincorporated Calvert County, Calvert County
  • 🏒 CompanyNatelli Holdings
  • 🌳 Size133 acres
  • πŸ”Œ Where the power comes fromGrid power through Southern Maryland Electric Cooperative (SMECO).
  • πŸ’§ WaterTreated (non-drinking) water from the Solomons Wastewater Treatment Plant
  • ❄️ CoolingCooling with non-potable water
  • πŸ’΅ Cost$3 billion
  • πŸ’Έ Tax breaksDeveloper offered a $30 million regional park across the road.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • March 24, 2026
    Natelli Holdings presented its plan to county commissioners and asked to buy 133 acres of county land.
  • Aug 18, 2026
    County commissioners passed a six-month pause on new data center applications.

Local votes and rules

⏸️ Pause on new data centers

County commissioners voted unanimously for a six-month pause on new data center development while the county reviews its rules. It came days after Amazon dropped plans for data centers at the Calvert Cliffs nuclear plant.

Aug 18, 2026

βœ‹ Turned down

Commissioners voted 2-3 against drafting a two-year data center pause. In a separate 3-0 vote (two abstained), they told staff to draft zoning changes to remove data centers from light industrial and mixed-use zones.

April 7, 2026
πŸ›°οΈ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Data center developer proposes site and park in Lusby Β· Calvert Recorder (Southern Maryland News) Β· March 25, 2026
  2. Amazon abandons plans for data center campus at Md.'s Calvert Cliffs nuclear plant Β· Maryland Matters via WTOP Β· Aug 4, 2026